Loading...
(A) According to SDCL § 31-32-3.1, intentional dumping on highway right-of-way is prohibited.
(B) The state right-of-way on Highway 18 is described as:
(1) McDonald’s Restaurant, west to Edwards Oil and Anderson Tire Company is 12 feet and four inches from back of curb;
(2) From west of Edwards Oil to the east side of the bridge is 42 feet and four inches;
(3) At Country Club Motel five feet and four inches from back of curb; and
(4) Beginning at the corner of East 3rd and Highway 18, to East 7th Street, the right-of-way is 23 feet and four inches from back of curb.
(C) Any snow falling on the right-of-way may be pushed into the street. However, additional snow from other areas, including parking lots, may not be pushed or piled on any highway right-of-way property.
(Prior Code, § 8.02.02) (Ord. 517, passed - -; Ord. 731, passed - -) Penalty, see § 94.999
EXCAVATIONS
(A) Any person or utility shall obtain an alley/street excavation permit prior to making, causing or permitting to be made, any excavation in or under the surface of any public street, alley, sidewalk or other public place for the installation, repair or removal of any pipe, conduit, duct or tunnel, or for any other purpose.
(B) The City Council shall periodically set the required cost of alley/street excavation permits through the ordinance process.
(C) The City Superintendent shall approve all work prior to the issuance of a permit.
(D) The person so applying shall deposit with the City Street Department, in the form of cash or certified check, an amount of not less than $100 per excavation.
(Prior Code, § 5.03.01) (Ord. 798, passed - -) Penalty, see § 94.999
The responsible party shall obtain a permit on the next working day if an emergency street cut, opening or excavation is made; however, the city shall be contacted prior to the commencement of any work to ensure compliance with § 94.058 and the responsible party is responsible for any city overtime expenses.
(Prior Code, § 5.03.02) (Ord. 798, passed - -)
(A) In making excavations in the streets or highways for the laying of service pipes or making repairs, the paving or earth must be deposited in a manner that will occasion the least inconvenience to the public, and provide for the passage of water along gutters.
(B) All openings into paved streets and sidewalks shall have saw cut edges if not at cold joints.
(Prior Code, § 5.03.03) (Ord. 226, passed - -; Ord. 731, passed - -; Ord. 798, passed - -)
No persons shall make any excavation in any street or highway, within six feet of any laid water pipe while the ground is frozen, or dig up or uncover so as to expose the frost any water pipe, except by permission of the City Superintendent.
(Prior Code, § 5.03.05) (Ord. 226, passed - -; Ord. 731, passed - -; Ord. 798, passed - -) Penalty, see § 94.999