1116.06 APPLICATION PROCEDURES.
   (a)   Soil Disturbing Activities Submitting a Stormwater Pollution Prevention Plan (SWP3). The applicant shall submit three (3) sets of the SWP3 and the applicable fees to the City of Wickliffe as follows:
      (1)    For subdivisions: After the approval of the preliminary plans and with submittal of the improvement plans.
      (2)    For other construction projects: Before issuance of a building permit by the Building Commissioner.
      (3)    For general clearing projects: Prior to issuance of a grading permit by the Building Commissioner.
   (b)    Soil Disturbing Activities Submitting an Abbreviated Erosion and Soil Control Plan (SWP3). The applicant shall submit three (3) sets of the Abbreviated SWP3 and the applicable fees to the City Engineer as follows:
      (1)   For single-family home construction: Before issuance of building permit or grading permit by the Building Commissioner.
      (2)   For other construction projects: Before issuance of a grading permit by the Building Commissioner.
      (3)   For general clearing projects: Before issuance of a grading permit by the Building Commissioner.
   (c)    The City Engineer and the Lake SWCD shall review the plans submitted under
Section 1116.06 (a) or (b) for conformance with this regulation and approve, or return for revisions with comments and recommendations for revisions. A plan rejected because of deficiencies shall receive a checklist or narrative report stating specific problems and the procedures for filing a revised plan.
   (d)    Soil disturbing activities (including mechanized clearing) shall not begin and zoning, building, or grading permits shall not be issued without:
      (1)    Approved SWP3 or Abbreviated SWP3
      (2)    NOI submittal to Ohio EPA and NPDES permit covered issued
      (3)    Physical marking in the field of protected areas or critical areas, including wetlands and riparian areas
      (4)    Installation of construction entrances, perimeter sediment barriers and other erosion and sediment controls that must be in place to address initial site conditions.
   (e)    SWP3 for individual sublets in a subdivision will not be approved unless the larger common plan of development or sale containing the sublet is in compliance with this regulation.
   (f)   The developer, engineer and contractor, and other principal parties, shall meet
with the City Engineer for a Pre-Construction Meeting no less than seven (7) days prior to soil-disturbing activity at the site to ensure that erosion and sediment control devices are properly installed, limits of disturbance and buffer areas are properly delineated and construction personnel are aware of such devices and areas. Pre-Construction Meetings for Abbreviated SWP3s may be waived at the discretion of the City Engineer.
   (g)   Approvals issued in accordance with this regulation shall remain valid for one (1) year from the date of approval.
(Ord. 2022-48. Passed 10-10-22.)