1175.04 PRELIMINARY PLAT REQUIRED.
   After the pre-application sketch meeting is held, the subdivider shall submit a preliminary plat of the proposed subdivision which shall conform with the requirements set forth in Sections 1175.05 to 1175.11, inclusive. The Preliminary Plat shall include all the property which the subdivider ultimately plans to subdivide.
(Ord. 2021-17. Passed 9-8-21.)
   1175.05 APPLICATION FOR TENTATIVE APPROVAL. 
   An application for the tentative approval of the preliminary plat on forms provided by the Village, together with a minimum of ten (10) copies of the preliminary plat and the supplementary information specified in Section 1175.06 to 1175.11, inclusive, shall be submitted to the Village Planning Commission's designated representative at least fourteen (14) days and not more than thirty (30) days prior to the meeting of the Commission at which action is requested. The preliminary plat shall be prepared by an Ohio registered professional engineer.
(Ord. 2021-17. Passed 9-8-21.)