§ 52.081 WATER METER INSTALLATION PROCEDURE.
   (A)   Customers shall pay tap fees and deposits as per town resolution. If not paid by the arranged installation date, the meter will not be set. All fees must be paid prior to the installation.
   (B)   Customers shall arrange for his or her contractor to contact the utility personnel at 405-356-2476 to schedule a date for new service to be installed.
   (C)   There is a minimum of ten days’ notice required for new service installs. Every effort will be made to do the installation within these ten days. However, occasionally emergency situations arise which would make this impossible.
   (D)   Customers receiving new service after July 1, 2022, are required to install a shut-off valve in his or her service line, after the meter and outside the meter can. This will allow the customer to turn on and off his or her water, without having to use the meter yoke valve.
(Ord. passed 7-1-2022)