All line extension exemptions shall be required to have WPWA Board approval and all applicable DEQ permits and fees. When permit is approved by DEQ and all easements needed are in place, customer may install said line extension per DEQ and WPWA specifications and regulations. All labor, materials and other appurtenances required to install the line extension shall be at the customer’s expense. After the line is installed and inspected by the WPWA, tested and required sufficiency certifications filed, then the WPWA will accept ownership and responsibility for operation and maintenance of said line extension. At that time, customer taps may be installed per WPWA meter tap policies. All fees shall be paid prior to installation of meters.
(Ord. passed 7-1-2022)