The owners of lots and lands bounding and abutting upon proposed sidewalks to be constructed, in accordance with the plans and specifications of the City, shall construct such sidewalks abutting their respective properties within a period of thirty days after the service of notice that such construction is necessary; and, if such construction is not completed within such period of thirty days, then Council shall have the same done and the cost expended therein shall be assessed upon the property of each defaulting owner, except for the cost of engineering, inspection and contingencies and legal advertising, and made a lien thereon, to be collected in the manner provided by law, with penalty and interest as provided by law.
The City shall assume any costs of engineering, inspection, contingencies and legal advertising as set forth in this section, which costs shall not be assessed against the property owners.
(Ord. 8186/75. Passed 4-14-75.)