§ 50.40 WATER AND SEWER TAP FEES.
   The following water and sewer tap fees shall be charged for all connections made to the water and sewer sanitary sewer system of the city and it shall be the duty of the Municipal Water and Sewer Works to collect the fees listed below. Tap fees are the same for customers inside and outside the city limits.
   (A)   Residential units. For the purpose of this subchapter, a residential unit is defined as a system of one or more rooms arranged for the separate living of an individual or family and, equipped for housekeeping.
         Unit               Fee   
      (1)   Single-family residential unit   $2,000.00
         (includes one 3/4” meter
         installation)
      (2)   Multi-family residential units -    
         single meter
         (First unit, includes one 3/4”    $2,000.00
         meter installation)
         Each additional unit (does not   $1,000.00
         (include cost of separate meter)
 
      Example: Four-plex apartment building
      with one meter:
      First unit:               $2,000.00
      Units 2, 3, & 4 ($1,000 x 3):      $3,000.00
      Total:                  $5,000.00
      (3)   Multi-family residential units - multiple meters. Should a multi-family residential unit require a separate meter for each residential unit, the cost shall be $2,000.00 for the first 3/4” meter and $1,200.00 for each additional 3/4” meter.
      Example: Four-plex apartment building, multiple meters
      First unit               $2,000.00
      Units 2, 3 and 4 ($1,200 x 3)      $3,600.00
      Total                  $5,600.00
   (B)   Commercial units. For the purpose of this subchapter, a commercial unit is defined as office buildings, retail store buildings to be used for commercial, professional or nonresidential undertaking.
         Unit               Fee  
      (1)   Single - office building      $2,000.00
         (includes one 3/4” meter
         installation)
      (2)   Single - retail store building   $2,000.00
         (includes one 3/4”    meter
         installation)
      (3)   Multi-commercial units - office
         building and retail store building
         First unit (includes one 3/4”   $2,000.00
         meter installation)
         Each additional unit         $1,000.00
         (does not include cost of
         separate meter)
      (4)   Should a multi-commercial unit require a separate meter for each unit, the cost shall be $2,000.00 for the first 3/4” meter and $1,200.00 for each additional 3/4” meter.
(Ord., passed 5-3-88; Am. Ord., passed 1-5-93; Am. Ord. 96-25, passed 12-3-96; Am. Ord. 99-15, passed 6-15-99)
   (C)   Special commercial. For the purpose of this subchapter special commercial is defined as to include connections for use by hotels, motels, hospitals, clinics, nursing homes, or education buildings, whether publicly or privately owned and whether operated for profit or nonprofit.
      (1)   Special commercial base       $3,500.00
         (Includes 2” meter)
         Fee for each room made
         available for occupancy by
         customers of a hotel or motel,
         or by patients of a hospital
         or nursing home or rooms to be
         used as classrooms in an
         educational building          $150.00
      (2)   Example: 50 unit motel
         Base fee             $3,500.00
         Rooms (50 x 150)          $7,500.00
         Total               $11,000.00
   (D)   Industrial units. Industrial units shall include any facility established for the purpose of manufacturing or processing goods. The fee for connection into the water and sanitary sewer system of any industrial unit shall be based on the size of the water meter.
   (E)   Residential units with sewer only. Sewer assessment charges for residential users outside the city corporate limits not receiving city water service shall be:
            Unit              Fee
            First unit         $1,500
            Each additional unit       1,500
(Ord., passed 12-5-85; Am. Ord., passed 5-3-88; Am. Ord. 96-25, passed 12-3-96; Am. Ord. 99-15, passed 6-15-99)
   (F)   Tap Fees. Tap fees in § 50.40(A) and (B) above are based on the charge for a 3/4” meter ($2,000.00), and the tap fee for § 50.40(C) is based on a 2” meter ($3,500.00) Any deviations to those sizes shall be based on the following fee structure:
      3/4”         =   $2,000.00
      1”         =   $2,300.00
      1.5”         =   $3,100.00
      2”         =   $3,500.00
      Larger than 2”    =   $2,000.00 plus customer provides the installation of the meter as specified by the city.
   (G)   Temporary Water Meter. Prior to the provision of any water service for any residential, commercial, special commercial or industrial new construction, or for other temporary service, the property owner or contractor must apply to the city and pay a thirty- five dollar ($35.00) installation fee and a two thousand dollar ($2,000.00) refundable deposit. Upon payment of such fee, the city will install a temporary water meter which shall be utilized to provide water to the subject property for a period of up to ninety (90) days. The property owner or contractor will be billed monthly for water usage, including appropriate taxes and Kentucky River Authority Withdrawal fees. There will be no sewer charge associated with temporary water meters.
(‘77 Code, § 17-108)(Ord., passed 12-19-74; Am. Ord., passed 12-6-77; Am. Ord. 1-5-93; Am. Ord. 96-25, passed 12-3-96; Am. Ord. 99-12, passed 6-15-99; Am. Ord. 99-13, passed 6-15-99; Am. Ord. 99-15, passed 6-15-99; Am. Ord. 2006-32, passed 1-3-07; Am. Ord. 2020-9, passed 1-21-20)