Before any person shall construct or contract for the construction of sewerage systems, sewerage system extensions, or waste treatment works or shall install any such process, device or equipment, either in whole or in part, an application for approval to construct the contemplated works shall be made to the director on forms provided by the director. The director shall act on the complete application within thirty (30) days upon receipt thereof by designating either approval or disapproval. In case of a disapproval, the director shall state in writing the reasons for the disapproval. No construction shall be commenced until approval has been obtained from the director.
(Ord. No. 4207, § 1, 7-8-74; Ord. No. 4594, § 3, 11-22-76)