5-1-13: EXEMPTION FROM WMP REQUIREMENTS:
   (A)   A WMP shall not be required for any of the following types of projects:
      1.   Projects and construction activity that only requires a plumbing, electrical, or mechanical permit.
      2.   A seismic tie-down project.
      3.   The installation of new fencing, but not replacement of existing fencing.
      4.   The installation of pre-fabricated patio enclosures and covers when no foundation or other structural building modifications are required.
      5.   The installation of pre-fabricated accessory structures such as signs or antennas which do not require structural building modifications.
      6.   City-sponsored projects that have been specifically exempted from the City.
      7.   Emergency demolition which are necessary to protect the public health and safety.
      8.   Projects, as determined by the Director of Public Works or his or her designee, not generating construction or demolition waste.
   (B)   Appeal Of Diversion Requirements: An applicant may appeal to the City Manager of a decision of the Director of Public Works decision to deny an exemption. Notice of appeal of the Director of Public Works decision must be filed with the City Manager's office within ten (10) calendar days of the date of the decision being appealed. The notice of appeal shall set forth in concise language the particular decision or decisions complained of and the reason why the person feels aggrieved thereby. Failure to file a notice of appeal within the time prescribed herein constitutes a waiver of any objection to the decision(s) of the Director of Public Works and such decision(s) shall be final; otherwise, the decision of the City Manager is final. (Ord. 840-21, 5-4-2021)