3-1.5-7: RESCORE INSPECTION:
At the discretion of the permittee, a rescore inspection may be requested to reassess compliance.
   (A)   A rescore inspection must be requested by the permittee on a standardized form as determined by the department within seven (7) days of the original inspection. Only one rescore inspection may be requested within each fiscal year.
   (B)   The director shall conduct a rescore inspection within seven (7) days of receiving the request and submission of the inspection fee by the permittee.
   (C)   At the conclusion of the rescore inspection, the inspection summary report shall be issued based upon the scoring method set forth in this chapter.
   (D)   A requested rescore inspection is separate and independent of all inspection as determined by the director. (Ord. 727-07, 1-2-2007, eff. 7-1-2007; amd. Ord. 836-20, 5-5-2020)