943.06 APPLICATION PROCEDURES.
   (a)   The applicant shall attend a Concept Plan Meeting with the County Drainage Engineer, Summit County Department of Community and Economic Development, Summit SWCD, Summit County Department of Sanitary Sewer Services, Summit County General Health District and others to discuss the proposed project, review the requirements of this Chapter, identify unique aspects of the project that must be addressed during the review process, and establish a preliminary review and approval schedule. The applicant will be required to submit a fee in accordance with Section 943.14(a) of this Chapter.
 
   (b)   Following the Concept Plan meeting, the applicant shall submit two (2) sets of a Preliminary Comprehensive Storm Water Management Plan (Preliminary Plan), and the applicable fees in accordance with Section 943.14(b) of this Chapter, to the County Drainage Engineer. The Preliminary Comprehensive Storm Water Management Plan shall show the proposed property boundaries, setbacks, dedicated open space, public roads, water resources, storm water control facilities, and easements in sufficient detail and engineering analysis to allow the County Drainage Engineer to determine if the site is laid out in a manner that meets the intent of this Chapter and if the proposed storm water management practices are capable of controlling runoff from the site in compliance with this Chapter.
 
   (c)   On approval of the Preliminary Plan, the applicant shall submit two (2) sets of a Final Comprehensive Storm Water Management Plan (Final Plan), and the applicable fees in accordance with Section 943.14(b) of this Chapter, to the County Drainage Engineer for approval. The Final Plan shall meet the requirements of Section 943.08 of this Chapter. One set of the Final Plan shall be submitted to Summit SWCD, as required by the Storm Water Pollution Prevention Plan (SWP3).
 
   (d)   The County Drainage Engineer shall review the Preliminary and Final Plans, and shall approve or return with comments and recommendations for revisions. A Preliminary or Final Plan rejected because of deficiencies shall receive a narrative report stating specific problems and the procedures for filing a revised Preliminary or Final Plan. Final approval of the Plans shall not be given until the Summit SWCD has approved the SWP3.
 
   (e)   The Final Plat shall not be approved, and land clearing and soil-disturbing activities shall not begin, without an approved Comprehensive Storm Water Management Plan, and an approved SWP3.
 
   (f)   Approvals issued in accordance with this Chapter shall remain valid for two (2) years from the date of approval. If regulations for storm water management change prior to the beginning of active construction, the County Drainage Engineer may require new approvals.
(Ord. 2013-364. Adopted 8-26-13; Ord. 2015-555. Adopted 12-14-15.)