923.07 CONSTRUCTION SERVICE FEE.
   (a)   All persons constructing privately financed sanitary sewer projects within the Summit County Metropolitan Sewer District shall pay a construction service fee for engineering, inspection and administrative functions performed by the County.
   (b)   The following construction service fees shall be paid at the time of the pre-construction conference after the Director of the Department of Sanitary Sewer Services has approved the project for construction, which approval shall be valid for a period of one (1) year.
Charge & Customer Type
Construction Service Fees ($ per Unit)
Wastewater Treatment Plants ($ per gallon per day of capacity)
January 1, 2022
January 1, 2023
January 1, 2024
January 1, 2025
January 1, 2026
$1.01
$1.03
$1.05
$1.07
$1.09
Pump Stations ($ per gallon per minute of capacity)
$17.85
$18.21
$18.58
$18.95
$19.33
Sanitary Sewer Lines and Force Mains ($ per linear foot)
$4.72
$4.82
$4.92
$5.01
$5.11
(Ord. 2006-550. Adopted 12-18-06; Ord. 2011-476. Adopted 11-21-11; Ord. 2012-452. Adopted 12-10-12; Ord. 2013-507. Adopted 12-10-13; Ord. 2014-526. Adopted 12-8-14; Ord. 2015-118. Adopted 3-30-15; Ord. 2015-555. Adopted 12-14-15; Ord. 2021-349. Adopted 12-6-21.)
   (c)   Requests for overtime inspection services shall be approved by the Director and shall be billed at the rate of thirty-nine dollars and sixty cents ($39.60) per hour. Overtime shall be accrued in one-half (½) hour increments only.
(Ord. 2006-550. Adopted 12-18-06.)