1242.04 WITHHOLDING PERMITS.
   (a)    Amendment Pending. No building permit or certificate of occupancy shall be issued during the period in which an amendment which would affect the building or use applied for has been recommended by the Planning Commission or introduced by Council. However, an application for a permit or certificate shall not be withheld for more than ninety days after the application was officially submitted.
   (b)    Nonconforming Lot. No building permit shall be issued for a one or two-family building unless the residential lot shall abut upon a public street; the utilities, pavement and all other required improvements have been constructed, or their construction guaranteed; the lot is located in a duly recorded subdivision or approved by the Planning Commission with no plat required.
(Ord. 2012-085. Passed 9-17-12.)