(A)
When the proposed development on the site requires review and approval by the Planning Commission, copies of complete Stormwater Management Plan and supporting data shall be filed with the Building Department in accordance with the submission schedule of the Planning Commission. The City Engineer or their representative shall review the proposed development for compliance with the Stormwater Management requirements herein and provide recommendations for consideration of the Planning Commission.
(B) The Planning Commission shall review these plans as submitted, together with the recommendations of the City Administrator, Building Official, and City Engineer. If the Commission approves the plans, the Building Official and City Engineer shall ensure compliance by the property owner/applicant with the construction plans submitted for construction permits.
(C) Every Stormwater Management plan approved by the Planning Commission shall expire with the expiration of Planning Commission approval as provided by the Zoning Code.
(D) In order to ensure that emergency measures could be taken by the city if the water management and sediment control measures are not implemented according to the agreed upon plan, a performance bond in the amount of the cost of the Stormwater Management Plan measures shall be required to be filed with the city. The City Engineer shall receive a construction estimate for the cost of the Stormwater Management Plan measures from the property owner/applicant for review, and shall set the amount of the bond. This bond shall include post-construction best-management practices. Said performance bond shall authorize immediate payment to the City of Springdale upon certification by the City Administrator, that necessary emergency work must be done immediately to ensure proper water management and sediment control as a result of the landowner's failure to complete or adhere to the approved Stormwater Management Plan.
(E) When the proposed development on the site does not require review and approval by the Planning Commission, the site plans shall be submitted to the Building Department as part of the construction submittal documents for permit per § 152.10, and be reviewed and approved by the City Engineer relative to proposed work in the right-of-way.
(F) For any new construction or alterations to an existing site, the owner shall pay any applicable fees, including the processing base fee, stormwater management fee, and penalty fees, as set forth in § 152.20(G). The processing base fee is intended to address the cost incurred by the Building Official in processing the permit application. The Stormwater Management Fee is intended to address the cost incurred to review and inspect the new work, which is authorized by this chapter. These fees for construction permit are in addition to the applicable fees and costs incurred during review and approval of the Planning Commission process.
(Ord. 25-1987, passed 3-18-87; Am. Ord. 40-2010, passed 12-15-10; Am. Ord. 40-2022, passed 12-21-22; Am. Ord. 21-2023, passed 4-19-23)