824.02 BUILDING REQUIREMENTS; FLOOR PLANS.
   (a)   Self-service or coin-operated dry cleaning locations shall be approved by the Building Department prior to the installation of equipment. A floor plan showing the building outline, any joint or adjacent occupancies and all equipment shall accompany the license application.
   (b)   Approval of plans will not be granted for a building occupied in part as a dwelling.
   (c)   A building should be a single story structure with a concrete floor in good condition. Installations in buildings of other types may be approved upon application, provided that adequate methods are used to protect health. The requirements should take into consideration proper ventilation, confinement of solvent within the dry cleaning service area and appropriate segregation of all building areas and equipment. Solvent systems shall not be installed in any basement or other location difficult to ventilate. Complete information about the building and its construction shall be included in the plans.
   (d)   All establishments shall meet all other applicable requirements of these Codified Ordinances.
(1974 Code § 7.232)