§ 1042.06 INSPECTIONS.
   (a)   The applicant for the building sewer permit shall notify the City Engineer at least 24 hours in advance of commencement of work. He or she shall request inspections from the City Engineer or his or her representative for the following items:
      (1)   All building sewer pipe laid in trench;
      (2)   All connections to existing building sewers;
      (3)   All repairs, corrections and/or additions to existing building sewers; and
      (4)   Test tee and riser inspections as specified in § 1042.24.
   (b)   No backfilling of any of the above items shall be done until the work under such items has been duly inspected and approved by the City Engineer and/or his or her representative. Such tests as are necessary to ensure that there are no storm drains connected to the sanitary sewer, or sanitary sewage drains connected to the storm sewer, may be required by the City Engineer and/or his or her representative.
(Ord. 1979-33, passed 5-7-1979)