A DRAINAGE SYSTEM COST RECOVERY is the process by which 50% of the applicable cost of the storm water drainage system is collected from all developing properties. The STORM WATER DRAINAGE SYSTEM applicable costs for drainage system cost recovery includes regional detention facilities excluding land, storm drainage appurtenances eligible for reimbursement pursuant to Reimbursement Procedures for Drainage System Cost Recovery- Executive Order, drainageway improvements or storm drainage facilities approved by city engineer. A REGIONAL DETENTION CHARGE is the process by which 50% of the cost of land acquisition for regional detention facilities is collected from development of parcels contributing stormwater runoff to a regional detention facility. REGIONAL DETENTION FACILITIES are identified in the Stormwater BMP Master Plan dated July 2003 and subsequent updates by city engineer.
(1992 Code, § 41-86) (Ord. 5-02, passed 1-14-2002; Ord. 97-03, passed 10-14-2003; Ord. 113-18, passed 12-4-2018)