Loading...
An applicant shall file all of the following with the Township Assessor, or other official designated by the governing body, for review and approval of a proposed land division before making any division either by deed, land contract, lease for more than one year, or for building development.
(A) A completed application form on such form as may be provided by the Township Board.
(B) Proof of fee ownership of the land proposed to be divided.
(C) A tentative parcel map drawn to scale including an accurate legal description of each proposed division, and showing the boundary lines, approximate dimensions, and the accessibility of each division for automobile traffic and public utilities; as well as the location of existing structures relative to the proposed boundary lines.
(D) Proof that all standards of the State Land Division Act and this chapter have been met.
(E) If a transfer of division rights is proposed in the land transfer, detailed information about the terms and availability of the proposed division rights transfer.
(F) Pay the applicable fee. Said fee shall be established by a fee schedule covering the costs of review of the application and administration of this chapter and the State Land Division Act as set from time to time by resolution of the Township Board.
(Ord. 97-3, passed 5-28-1997; Ord. 021-07, passed 11-10-2021)
(A) The Township Assessor or other township designee shall approve or disapprove the land division within 45 days after receipt of a complete application conforming to this chapter’s requirements and the State Land Division Act, and shall promptly notify the applicant of the decision, and if denied, the reasons for denial. In determining whether to approve or disapprove a land division, the Assessor or designee shall seek the advice or comments of the Zoning Administrator as to whether the proposed split is in compliance with the minimum parcel size and accessibility requirements of the zoning ordinance.
(B) Any person or entity aggrieved by the decision of the Assessor or designee may, within 30 days of said decision, appeal the decision to the governing board of the township, or such other body or person designated by the governing body, which shall consider and resolve such appeal by a majority vote of said board or by the appellate designee at its next regular meeting or session affording sufficient time for a 20-day written notice to the applicant (and appellant where other than the applicant) of the time and date of said meeting and appellate hearing. The decision of the Township Board shall be a final decision for purposes of judicial review.
(C) The Assessor or designee shall maintain an official record of all approved and accomplished land divisions or transfers.
(D) Approval of a division is not a determination that the resulting parcels comply with other ordinances or regulations. Any notice of approval shall include a statement to this effect.
(E) The township and its officers and employees shall not be liable for approving a land division if building permits for construction on the parcel area are subsequently denied because of inadequate water supply, sewage disposal facilities or otherwise, and any notice of approval shall include a statement to this effect.
(Ord. 97-3, passed 5-28-1997; Ord. 021-07, passed 11-10-2021)
A proposed land division reviewable by the township shall be approved if the following criteria are met:
(A) The width of each resulting parcel shall comply with the applicable minimum parcel (lot) width/frontage requirements of the township zoning chapter.
(B) The area of each resulting parcel shall comply with the applicable minimum parcel (lot) requirements of the township zoning chapter.
(C) Except for parcels meeting the requirements of division (C)(1) herein, the ratio of depth to width of any parcel created by the division does not exceed a four to one ratio exclusive of access roads, easements, or non-development sites. The depth of a parcel created by a land division shall be measured within the boundaries of each parcel from the abutting road right-of-way to the most remote boundary line point of the parcel from the point of commencement of the measurement, or from that side of the parcel nearest the road accessed by an approved and recorded easement.
(1) Exception to permit a greater depth-to-width ratio. In the following circumstances, the land division officer is authorized to exceed the depth to width ratio provided in this chapter:
(a) Exceptional or topographical conditions, such as the existence of unbuildable or protected swamps and/or wetlands, extraordinary natural topographical changes such as steep slopes or irregular terrain, eliminating or reducing the potential for further division based on accessibility. In such case, the land division officer shall so identify the condition and indicate that no further divisions shall be permitted unless the depth-to-width ratio in this chapter is met.
(D) The proposed land division(s) comply with all requirements of this chapter and the State Land Division Act.
(E) All parcels created and remaining shall have adequate accessibility, or an area available therefor, for public utilities and emergency and other vehicles.
(Ord. 97-3, passed 5-28-1997; Ord. 14-02, passed 7-9-2014; Ord. 021-07, passed 11-10-2021)
(A) Any division of land in violation of any provision of this chapter shall not be recognized as a land division on the township tax roll and no construction thereon which requires the prior issuance of a construction or building permit shall be allowed. The township shall further have the authority to initiate injunctive or other relief to prevent any violation or continuance of any violation of this chapter.
(B) Any unlawful division or split shall also be voidable at the option of the purchaser and shall subject the seller to the forfeiture of all consideration received or pledged therefor, together with any damages sustained by the purchaser, recoverable in an action at law.
(Ord. 97-3, passed 5-28-1997; Ord. 021-07, passed 11-10-2021) Penalty, see §
151.99
(A) Any violation of this chapter shall constitute a basis for such judgement, write or order necessary to compel compliance with the chapter and/or to restrain and prohibit continuation of the violation, or other appropriate relief in any court of competent jurisdiction, in addition to any other relief or sanction herein set forth or allowed by law. Each day that an ordinance violation continues constitutes a separate offense.
(B) A violation of this chapter is a municipal civil infraction as defined by Michigan statute and shall be punishable by a civil fine determined in accordance with the following schedule:
Minimum Fine | Maximum Fine | |
1st offense | $150 | $500 |
2nd offense | 325 | 500 |
3rd offense | 500 | 500 |
(C) Additionally, the violator shall pay costs which may include all expenses, direct and indirect, which the township has incurred in connection with the municipal civil infraction.
(Ord. 97-3, passed 5-28-1997; Ord. 021-07, passed 11-10-2021)