808.19 BAILING, SWABBING AND TESTING WELLS.
   No person shall bail, swab or test any well from sundown until sunrise, during a period when gas may settle on the ground, during any electrical storm or during any period when the velocity of the wind is greater than twenty-five miles per hour. During the process of bailing, swabbing or testing any well, if gas is present and escaping, all electrical energy shall be shut off from all wires furnishing energy for lights on or about any derrick and only flood lights which are not less than forty feet from such well shall be used during such bailing. If a drill stem test is taken, reverse circulation shall be maintained at all times during such test.
(Ord. 907. Passed 9-26-77.)