§ 25-7-77 CONSTRUCTION; COMPLETION.
   The proposed construction shall begin within 12 months after approval of the application by the Planning Commission. A minimum of 50%, in terms of cost, of the total construction (including improvements other than buildings) shown on the approved plan shall be completed within a period of two years following approval; otherwise, approval of the plan will expire. The period of time for completion of the development may be extended from time to time by the Planning Commission, upon showing of good cause by the applicant for the permit.
(Ord. 3639, passed - -2000)