The Electrical Inspector shall make the following inspections of electrical equipment installations:
(A) An “electrical rough-in” inspection when all conduit, boxes, wires troughs, raceways, cabinets, and panel boards to be installed are in place, before the view thereof has been obscured and before installing fixtures or devices;
(B) “Meter loop” inspection when all conduit, service entrance equipment, meter sockets, main service disconnects, and distribution panels are in place and all wiring from the point of service attachment to the point of distribution is in place, before current is permanently connected or restored;
(C) “Final electrical” inspection when all electrical equipment to be installed, including all outlets, receptacles, lights, switches, fixtures, appliances, motors, controls, devices, and apparatus are in place, completed, and operating; and
(D) Such other inspections or tests of apparatus as the Electrical Inspector shall deem necessary to determine compliance with provisions of this article.
(Ord. 1116, passed 2-25-1957; Ord. 2200, passed - -1976)