1 Sheet size is 24 x 36 incites.
2 Plan to show the following (minimum)
a Vicinity Map
b North Arrow
c Scale
d Existing improvements and proposed signing marking and signal improvements.
e Legend - Topo and Construction
f General Notes
g Engineer’s Signature
h License number and expiration date
i Details
j Stationing and Dimensions.
3 Submit 2 sets of plans tor checking
C General Noles (on all Plans)
1 All work shall be in accordance with Standard Specifications for Public Works Construction (Green Book), latest edition, with all supplements and City of San Bernardino Standard Drawings.
2 Approval of this plan by the City of San Bernardino does not constitute a representation as to the the accuracy of the location or of the existence or nonexistence of any underground utility pipe or structure within the limits of this project. The Contractor shall assume full responsibility for the protection of all utilities within the limits of the project. Contractor shall contact Underground Service Alert 48 hours prior to start of work.
3 Inspection shall be by the City of San Bernardino Department of Public Works. All requests for inspection shall be made at least 24 hours in advance of the proposed construction.
4 All existing pavement markings that are being relocated or removed shall be removed by sand blasting. No black-over painting of lines is permitted in the City.
5 During the period of construction, the Contractor shall furnish,.erect and maintain such warnings, signs, stops signs, barricades and other safety measures in conformance with the W.A.T.C.H manual or other City reference manuals listed.
D Additional notes that may be used as warranted by specific projects.
1 The Contractor shall provide safe and continuous passage for local pedestrian and vehicular traffic at all times.
2 Should any of the existing utilities or any other facilities, conflict with the proposed improvement the Contractor shall notify the Engineer and await the relocation and/or provide an alternate design.
3 The Contractor shall so conduct his operations as to offer the least possible obstruction and inconvenience to the public.
4 In accordance with generally accepted construction practices, the Contractor shall be solely and completely responsible for conditions of the job site, including safety of all persons and property during performance of the work and the Contractor shall fully comply with all state and Federal laws, rules, regulations, and orders relating to safety to the public and workmen.
5 Dust shall be controlled at all times by approved methods.
6 Public streets shall be kept clean and free from dirt and/or debris. The Contractor shall be responsible for all costs incurred in street cleaning necessitated by his operations.
7 Full street closure will not be permitted unless prior written approval is obtained from the Director of Public Works/City Engineer. Detour plans must be submitted for approval for all street closures and may be required for other types of detours under some circumstances. 48 hour notice will be required to the Cily and affected property owners prior to any closure.
8 On arterial streets, all full lane closures will require submittal of detour plans and/or signing plans with prior written approval by the Director of Public Works/City Engineer.
E Notes to Traffic Striping Plan.
1 Materials shall comply with Sub. Sec. 210-1.6, “Paint for Traffic Striping, Marking and Curb Marking”, of the Standard Specification for Public Works Construction (Greenbook) latest edition or equal supplement.
2 Traffic Paint shall be Fast Dry, Solvent Borne, Low Volatile Organic Compound (VOC) 250 unless otherwise specified.
3 Thermoplastic paint when specified shall be Reflectorized Alkyd.
4 New striping applications shall be done in two (2) coats.
5 Traffic control shall be according to the Work Area Traffic Control Handbook (WATCH) manual latest edition.
6 Raised Pavement Markers (RPM) when specified shall be consistent with CALTRANS Standard Specification Sec. 85, “Pavement Markers”, latest edition.
Any such additional notes that may be required for the completion of the plans and construction.