(1) For all projects sites designated as Tier A, a minimum of 14.4 percent of the total units constructed shall be affordable to and occupied by qualifying persons and families as defined elsewhere in this Code, so that a project sponsor must construct .144 times the total number of units produced in the principal project beginning with the construction of the tenth unit. If the total number of units is not a whole number, the sponsor shall round up to the nearest whole number for any portion of .5 or above.
(A) If the project sponsor is eligible for and elects pursuant to Section 415.5(g) to build off-site units to satisfy the requirements of this program, the sponsor shall construct 23 percent so that a sponsor must construct .23 times the total number of units produced in the principal project beginning with the construction of the tenth unit. If the total number of units is not a whole number, the sponsor shall round up to the nearest whole number for any portion of .5 or above.
(B) If the project sponsor elects pursuant to Section 415.5 to pay the fee to satisfy the requirements of this program, the sponsor shall meet the requirements of Section 415 according to the number of units required above if the project applicant were to elect to meet the requirements of this Section by off-site housing development. For the purposes of this Section, the City shall calculate the fee using the direct fractional result of the total number of units multiplied by the percentage of off-site housing required, rather than rounding up the resulting figure.
(2) For all project sites designated Tier B, a minimum of 16 percent of the total units constructed shall be affordable to and occupied by qualifying persons and families as defined elsewhere in this Code, so that a project sponsor must construct .16 times the total number of units produced in the principal project beginning with the construction of the tenth unit. If the total number of units is not a whole number, the sponsor shall round up to the nearest whole number for any portion of .5 or above.
(A) If the project sponsor is eligible for and elects pursuant to Section 415.5(g) to build off-site units to satisfy the requirements of this program, the sponsor shall construct 25 percent so that a sponsor must construct .25 times the total number of units produced in the principal project beginning with the construction of the tenth unit. If the total number of units is not a whole number, the sponsor shall round up to the nearest whole number for any portion of .5 or above.
(B) If the project sponsor elects pursuant to Section 415.5(g) to pay the fee to satisfy the requirements of this program, the sponsor shall meet the requirements of Section 415 according to the number of units required above if the sponsor were to elect to meet the requirements of this Section by off-site housing development. For the purposes of this Section, the City shall calculate the fee using the direct fractional result of the total number of units multiplied by the percentage of off-site housing required, rather than rounding up the resulting figure.
(3) For all project sites designated Tier C, a minimum of 17.6 percent of the total units constructed shall be affordable to and occupied by qualifying persons and families as defined elsewhere in this Code, so that a project sponsor must construct .176 times the total number of units produced in the principal project beginning with the construction of the tenth unit. If the total number of units is not a whole number, the sponsor shall round up to the nearest whole number for any portion of .5 or above.
(A) If the project sponsor is eligible for and elects pursuant to Section 415.5(g) to build off-site units to satisfy the requirements of this program, the sponsor shall construct 27 percent so that a sponsor must construct .27 times the total number of units produced in the principal project beginning with the construction of the tenth unit. If the total number of units is not a whole number, the sponsor shall round up to the nearest whole number for any portion of .5 or above.
(B) If the project sponsor elects pursuant to Section 415.5 to pay the fee to satisfy the requirements of this program, the sponsor shall meet the requirements of Section 415 according to the number of units required above if the sponsor were to elect to meet the requirements of this Section by off-site housing development. For the purposes of this Section, the City shall calculate the fee using the direct fractional result of the total number of units multiplied by the percentage of off-site housing required, rather than rounding up the resulting figure.
(c) Timing and Payment of Fee. Any fee required by Section 419.1et seq. shall be paid to the Development Fee Collection Unit at DBI at the time of and in no event later than issuance of the first construction document, with an option for the project sponsor to defer payment to prior to issuance of the first certificate of occupancy upon agreeing to pay a deferral surcharge in accordance with Section 107A.13.3 of the San Francisco .
(Added by Ord. 108-10, File No. 091275, App. 5/25/2010; amended by Ord. 55-11, File No. 101523, App. 3/23/2011; Ord. 219-12, File No. 120464, App. 10/23/2012, Eff. 11/22/2012, Oper. 1/15/2013; Ord. 62-13
, File No. 121162, App. 4/10/2013, Eff. 5/10/2013; Ord. 50-15
, File No. 150149, App. 4/24/2015, Eff. 5/24/2015)
AMENDMENT HISTORY