The following documents and other data, and as many additional copies thereof as may be required by the director of public works, shall be filed with the final or parcel map:
A. A submittal application.
B. A title report and guarantee of title from a title company.
C. A traverse indicating latitudes, departures, and coordinates and showing the mathematical closures.
D. Field notes as required by chapter 17.848.
E. The complete plans, profiles, cross sections, specifications and applicable permits for the construction and installation of improvements as required by chapter 17.848, Improvements.
F. A final grading plan. Submission of a final grading plan may be waived by the director of utilities when the submission of said plan is not required for proper grading, flood hazard mitigation and erosion control of the subdivision.
G. The agreement to make improvements and the security for the improvements as required by chapter 17.848.
H. Protective covenants, conditions, restrictions or affirmative obligations if required as a condition of approval of the tentative map.
I. Offers of dedication by separate instrument and accompanying title report if required as a condition of approval of the tentative map. Whenever an offer of dedication by separate instrument accompanies a final or parcel map, the final or parcel map shall not be accepted for filing by the director of public works until the offer of dedication has also been approved.
J. In areas subject to 100 year flood hazard, base flood elevation or depth of flow and floodway boundary shall be indicated or a separate document shall be recorded with the final or parcel map indicating floodway boundary and base flood elevation or depth of flow.
K. All other data required by law or as a condition of approval of the tentative map, including plans, reports, agreements, permits, fees, security or other requirements. (Ord. 2017-0009 § 23)