§ 7-4-6 INSPECTION PROCEDURES.
   (A)   The PWD will assist in the location of sewer lines in the vicinity of the proposed excavation.
   (B)   After the excavation has been made, if applicable, the PWD will inspect any disturbed or exposed water or sewer line to ensure that no damage has been done to the lines. If the excavation is for a new sewer service (to a line without an existing stub-out), during this inspection, the city operator will aid the contractor in tapping the sewer main with the use of city supplied tapping drill and contractor supplied pipe and fittings. In addition, a field diagram shall be made of the sewer service layout and filed with the City Clerk.
   (C)   Prior to backfill, the installation and excavation shall be inspected.
   (D)   During the backfilling procedure, to ensure that city standard procedures and materials are used, the project shall be inspected reviewed and corrected, if necessary.
   (E)   A final inspection will be made after resurfacing is completed.
(1992 Code, § 7-1-1206) (Ord. 07-01, passed 1-22-2007)