A drainage system shall be designed and constructed by the developer in accord with the Construction Standards of the City as required for the drainage of the surface water of the subdivision and each lot as follows:
(a) Enclosed Storm Sewer System (Standard). An enclosed storm sewer system shall be provided and connected to the existing storm sewer system and have a capacity to serve the subdivision and adjoining unsubdivided land as shown in the same drainage area on the City's sewer plans. The system shall include pipes, culverts, manholes, catch basins, drain inlets and a connection for each lot.
The storm water drainage system shall be designed by a registered engineer subject to the approval of the Building Division and in accordance with the most recent standards for engineering design of storm and sanitary sewerage and drainage facilities prepared by the City.
(b) Open Drainage System (Criteria). Subject to the approval of the Planning Commission, the developer may rechannel any watercourses through his property and may be required to deed in fee, dedicate or grant an easement to the City for a drainage channel not less in width than required by a a plan prepared by a registered engineer and in accord with Construction Standards of the City.
(Ord. 58-73. Passed 7-23-73.)