7-4-6: EFFECT OF PERMIT:
   A.   Authority Granted; No Property Right Or Other Interest Created: A permit issued by the village authorizes a permittee to undertake only certain activities in accordance with this chapter on village rights of way, and does not create a property right or grant authority to the permittee to impinge upon the rights of others who may have an interest in the rights of way.
   B.   Duration: No permit issued under this chapter shall be valid for a period longer than six (6) months unless construction is actually commenced within said period and is thereafter diligently pursued to completion.
   C.   Preconstruction Meeting Required: No construction shall begin pursuant to a permit issued under this chapter prior to attendance by the permittee and all major contractors and subcontractors who will perform any work under the permit at a preconstruction meeting. The preconstruction meeting shall be held at a date, time and place designated by the village with such village representatives in attendance as the village deems necessary. The meeting shall be for the purpose of reviewing the work under the permit, and reviewing special considerations necessary in the areas where work will occur, including, without limitation, presence or absence of other utility facilities in the area and their locations, procedures to avoid disruption of other utilities, use of rights of way by the public during construction, and access and egress by adjacent property owners.
   D.   Compliance With All Laws Required: The issuance of a permit by the village does not excuse the permittee from complying with other requirements of the village and applicable statutes, laws, ordinances, rules, and regulations.
   E.   As Constructed Permit Drawings: The permittee shall submit an as constructed set of drawings or plans to the village within ninety (90) days after the completion of the permitted work. The as constructed drawings or plans shall specifically identify the locations of the actual facilities as installed under the permit. If any deviation from the permit also deviates from the requirements of this chapter, it shall be treated as a request for variance in accordance with this chapter. If the village denies the request for a variance, then the permittee shall either remove the facility from the right of way or modify the facility so that it conforms to the permit and submit revised drawings or plans therefor. (Ord. 09-1-1, 1-6-2009; amd. Ord. 09-7-14, 7-7-2009)