Sec 122-632 Permits And Variances
   A.   Future uses. Except as specifically provided in subsections (A)(1), (2) and (3) of this section, no material change shall be made in the use of the land, no structure shall be erected or otherwise established, and no tree shall be planted in any zone hereby created unless a permit therefor shall have been applied for and granted. Each application for a permit shall indicate the purpose for which the permit is desired, with sufficient particularity to permit it to be determined whether the resulting use, structure, or tree would conform to the regulations in this division prescribed in this division. If such determination is in the affirmative, the permit shall be granted. No permit for use inconsistent with the provisions of this division shall be granted unless a variance has been approved in accordance with subsection (D) of this section.
      1.   In the area lying within the limits of the horizontal zone and conical zone, no permit shall be required for any structure or tree less than seventy-five (75) feet of the vertical height above the ground, except when, because of terrain, land contour, or topographical features, such structure or tree would extend above the height limits prescribed for such zones.
      2.   In areas lying within the limits of the approach zones, but at a horizontal distance of no less than four thousand two hundred (4,200) feet from each end of the runway, no permit shall be required for any structure or tree less than seventy-five (75) feet of vertical height above the ground, except when such structures or tree would extend above the height limit prescribed for such approach zones.
      3.   In the areas lying within the limits of the transition zones beyond the perimeter of the horizontal zone, no permit shall be required for any structure or tree less than seventy-five (75) feet of vertical height above the ground, except when such structure or tree, because of terrain, land contour, or topographical features, would extend above the height limit prescribed for such transition zones.
Nothing contained in any of the foregoing exceptions shall be construed as permitting or intending to permit any construction, or alteration of any structure, or growth of any tree in excess of any of the height limits established by this division except as set forth in Section 122-629(5).
   B.   Existing uses. No permit shall be granted that would allow the establishment or creation of an obstruction, or permit a nonconforming use, structure, or tree to become a greater hazard to air navigation than it was on the effective date of the ordinance from which this section is derived or any amendments thereto or than it is when the application for permit is made. Except as indicated, all applications for such permit shall be granted.
   C.   Nonconforming uses abandoned or destroyed. Whenever the Joint Airport Zoning Board determines that a nonconforming structure or tree has been abandoned or more than eighty percent (80%) torn down, physically deteriorated, or decayed, no permit shall be granted that would allow such structure or tree to exceed the applicable height limit or otherwise deviate from the zoning regulations.
   D.   Variances. Any person desiring to erect or increase the height of any structure, or allow the growth of any tree, or use property, not in accordance with the regulations prescribed in this division, may apply to the Board of Adjustment for a variance from such regulations. The application for a variance shall be accompanied by a determination from the Federal Aviation Administration as to the effect of the proposal on the operation of air navigation facilities and the safe and efficient use of navigable airspace. Such variances shall be allowed where it is duly found that a literal application or enforcement of the regulations will result in unnecessary hardship and relief granted, will not be contrary to the public interest, will not create a hazard to air navigation, will do substantial justice, and will be in accordance with the spirit of this division. Additionally, no application for variance to the requirements of this division may be considered by the Board of Adjustment unless a copy of the application has been furnished to the Airport Zoning Commission for advise as to the aeronautical effect of the variance. If the Airport Zoning Commission does not respond to the application within fifteen (15) days after receipt, the Board of Adjustment may act on its own to grant or deny the application.
   E.   Obstruction marking and lighting. Any permit or variance granted may, if such action is deemed advisable to effectuate the purpose of this division and is reasonable in its circumstances, be so conditioned as to require the owner of the structure or tree in question to install, operate, and maintain, at the owner's expense, such markings and lights as may be necessary. If deemed proper by the Board of Adjustment, this condition may be modified to require the owner to permit the City, at its own expense, to install, operate, and maintain the necessary markings and lights.
(Ord. No. 01-A14, § 7, 9-27-2001)