A. No grading work shall be done before a permit is issued therefor.
B. The permittee shall notify the city forty-eight hours prior to starting work at the beginning of the project and on each occasion where work has stopped for more than three consecutive working days.
C. The city shall have the right to inspect the work regularly for compliance with the requirements of this chapter and the conditions of the permit.
D. The city shall place shall special emphasis on inspection at critical times in the sequence of construction, such as immediately prior to July 15th, immediately prior to October 1st, immediately after the first significant rainfall of the season, and after every heavy storm.
E. The civil engineer who prepared the grading plans shall submit a progress report at the end of every month during which work was done.
F. The permittee must call for city inspection for any drainage device and the city must make its inspection before the device is covered. (Ord. 486 (part), 1986).