A. A public project of sixty thousand dollars ($60,000) or less may be performed by city force account, by negotiated contract, or by purchase order.
B. A public project greater than sixty thousand dollars $60,000 and less than or equal to two hundred thousand dollars ($200,000) may be let to contract by informal bid procedures, as established in § 3.34.040.
C. A public project of more than two hundred thousand dollars ($200,000) shall, except as otherwise provided in § 3.34.040(D), be let to contract by formal bidding procedure in accordance with all applicable provisions of the California Public Contract Code or successor statute.
D. The described project cost limits of subsections A through C shall be increased automatically as authorized pursuant to the adjustments made by the California Uniform Construction Cost Accounting Commission under Public Contract Code § 22020 or successor statute.
(Ord. 2019-02 § 2 (part), 2019; Ord. 2016-05 § 2 (part), 2016).