9.16.1.5   Consideration of Major Site Plans
   (A)   Review by Staff and the Planning and Zoning Board on Major Site Plans:
      (1)   The application and General Concept Plan shall be reviewed by the Village Planner and the Technical Review Committee for general compliance with the standards and requirements set forth in this Ordinance. The developer at their discretion may submit a sketch plan for initial review and comment. The comments of the Village Planner and the TRC shall then be provided to the applicant;
      (2)   The applicant may resubmit the General Concept Plan along with a written response to these comments for further review by the Village Planner and Technical Review Committee. The Village Planner shall review the resubmitted plan and then submit its comments about the resubmitted site plan to the applicant;
      (3)   The process continues until the General Concept Plan is ready to be presented to the Planning and Zoning Board for review;
      (4)   The Village Planner shall transmit the General Concept Plan materials to the Planning and Zoning Board, along with the recommendations of the Village Planner and the Technical Review Committee from the completion of staff review prior to a regularly scheduled meeting of the Board;
      (5)   The Planning and Zoning Board shall conduct a public hearing in accordance with section 4.1.2 of this ordinance and review the General Concept Plan, the recommendations of the Village Planner and the Technical Review Committee, and the requirements of this Ordinance, and formulate a recommendation to the Village Council for appropriate action on the site plan. Failure of the Planning and Zoning Board to make a recommendation to the Village Council within ninety (90) days of the first public meeting in which the item is on the agenda for consideration by the Board shall be considered a favorable recommendation.
   (B)   Action by Village Council on Major Site Plans: The application, the General Concept Plan, the recommendation of the Planning and Zoning Board, along with the staff report of recommendation of the Village Planner and other pertinent materials shall then be forwarded to the Village Council for action after a public hearing is held by the Village Council in accordance with section 4.1.2 of this ordinance. The Village Council shall review this information and either approve, approve with conditions, or reject the site plan:
      (1)   The Village Council may approve a General Concept Plan only if it meets the standards and requirements set forth in this Ordinance and provides for the dedications and improvements, or payments and guarantees in lieu thereof, required by this Section;
      (2)   If the Village Council rejects a General Concept Plan, then the reasons therefor shall be stated in the record of action on the General Concept Plan;
      (3)   Failure of the Village Council to act on the General Concept Plan within ninety (90) days of being placed on an agenda for consideration, the General Concept Plan and recommendations from the Planning and Zoning Board shall be deemed approval of the General Concept Plan, authorizing the applicant to proceed with preparing full site plan (Appendix D) drawings of the property in accordance with the General Concept Plan submitted to the Village Council. This time limit shall not apply where the delay in General Concept Plan approval is caused by the applicant's failure to obtain any special use approval required for the proposed development or where the applicant consents to such a delay.
      (4)   Upon approval of the General Concept Plan by the Village Council, the applicant shall prepare and submit site plans in accordance with Appendix D. Said site plans shall be reviewed using the minor site plan process. Upon Village Planner approval of the site plan, the major site plan shall be deemed approved.
   (C)   Flow Chart for Path for Major Site Plan Approval
(Ord. 21-12, passed 07-27-2021)