A. Establishment and Removal. Requests for establishment or removal of a golf course zone shall be processed in accordance with Chapter 18.91 (Rezoning Procedures), and is supplemented by the requirements outlined in this chapter.
B. Submission of Plan. The petitioners for a golf course zone shall submit a golf course preliminary development plan for the entire zone and its associated land uses at the time of application.
C. Notice.
1. Notice of all public hearings shall be given to owners of property within six hundred feet of the proposed golf course zone.
2. Failure to give notice shall not invalidate decisions made.
D. Effective Date and Phasing.
1. The certificate of compliance for the golf course zone shall be issued when the construction of the golf course and its supporting facilities have been completed in substantial compliance with the approved development plan.
2. If a golf course is constructed in phases, a construction schedule must be submitted and approved with the development plan.
3. A certificate of compliance for each phase of the golf course zone shall be issued only for that phase completed in substantial compliance with the approved development plan.
E. Grading Permits.
1. No clearing, brushing or grubbing, grading or development shall be allowed in the proposed golf course zone prior to approval of a Type 2 grading plan and the issuance of a grading permit.
2. A golf course grading plan will be accepted and approved only as an element of the required golf course development plan.
3. Grading permits will be issued in conjunction with grading plan review and approval by the department of transportation and flood control district.
(Ord. 2006-96 § 1 (part), 2006; Ord. 1986-187 § 1 (part), 1986; Ord. 1985-82 (part), 1985)