17.95.110: PERMITS:
   A.   It shall be unlawful for any person to erect, construct, reerect, or replace, any tower without first making application to the city and securing a building/zoning permit.
   B.   A building/zoning permit shall not be required for antennas and/or towers erected temporarily for test purposes, for emergency communication, or for broadcast remote pick up operations. Temporary antennas shall be permitted for a maximum of seventy two (72) hours unless specifically approved otherwise by the planning and zoning commission.
   C.   In addition to the findings required and conditions permitted for conditional use permits in this title, the commission shall make an additional finding concerning the duration of the conditional use permit. Upon finding that the conditional use permit is to be limited in duration, a condition limiting the duration and the basis for such a condition shall be included within the findings of fact and conclusions of law for the conditional use permit. (Ord. 1423, 2017)