(a) Fees for the examination of plans and applications for the issuance of permits, and for the original inspection and certificate of operation for the construction, installation, reconstruction or alteration of any process, fuel-burning, refuse-burning or control equipment within the jurisdiction of this Air Pollution Code, and for renewal of certificates of operation shall be as follows:
Permit and Initial Certificate
| Renewal Certificate
|
Permit and Initial Certificate
| Renewal Certificate
| |
(1) Process and Fuel-Burning Equipment for Each Unit. | ||
A. Of a rated input capacity of less than 250,000 BTU/HR
| $ 10.00
| $ 5.00
|
B. Of a rated input capacity of 250,000 BTU/HR and less than 1,000,000 BTU/HR
| 25.00
| 10.00
|
C. Of a rated input capacity of 1,000,000 BTU/HR and less than 5,000,000 | 00
| |
D. Of a rated input capacity of 5,000,000 BTU/HR or more.
| 100.00
| 50.00
|
(2) Refuse-Burning Equipment
| ||
A. Having a primary furnace volume of 4 cubic feet or less
| $ 5.00
| $ 5.00
|
B. Having a primary furnace volume over 4 cubic feet but less than 25 cubic feet
| 20.00
| 10.00
|
C. Having a primary furnace volume over 25 cubic feet but less than 75 cubic feet
| 00
| |
D. Having a primary furnace volume of 75 cubic feet or more
| 60.00
| 25.00
|
(3) Process Equipment. Process equipment requiring control by exhaust air ventilation in order to comply with sections on prohibited emissions.
| ||
A. Up to 300 scfm maximum
| 10.00
| 5.00
|
00
| ||
C. 1,001 to 5,000 scfm maximum
| 20.00
| 10.00
|
00
| ||
E. Over 10,000 scfm
| 75.00
| 25.00
|
(4) Air cleaning equipment and appurtenances. A separate permit shall be required and shall carry the same fees as the process equipment for which it is installed (see subparagraph (a)(3) hereof).
(b) The provisions of this Air Pollution Code shall apply within the City to all governmental units unless the imposition and collection of fees are prohibited by law.
(Ord. 221-70. Passed 7-19-71.)