(a) In any construction regulated by this chapter, all concrete suppliers shall, at the time of loading for delivery to a user, complete a form entitled the Residential Concrete Drive: Plant and Contractor's Report, Part I, which shall state:
(1) The delivery destination;
(2) The size of the load;
(3) The concrete mix;
(4) The total air content from all sources;
(5) The amount of water added at the plant;
(6) The admixture added;
(7) The amount of calcium chloride added; and
(8) The time of truck loading.
(b) In any such construction, the contractor or his or her agent shall complete a form entitled the Residential Concrete Drive: Plant and Contractor's Report, Part II, which shall state:
(1) The address or sublet number of the pour location;
(2) The time of arrival;
(3) The time of pour;
(4) The name of the builder or user;
(5) The name of the cement contractor;
(6) The amount of water added at the job site;
(7) The area temperature at the time of pour; and
(8) The curing compound used and the type of sealer used.
(c) An original and two copies of the Report shall be signed by the individuals completing the Report. The persons described in subsections (a) and (b) hereof do, by affixing their signatures to this Report, warrant that the statements contained therein are true, under penalty of law. The original shall be sent to the Building Commissioner within twenty-four hours of pouring, a copy shall be retained by the builder and a copy shall be retained by the supplier.
(d) A contractor shall not pour any concrete for which the Report indicates noncompliance with any specification stated in this chapter.
(e) The Building Commissioner or his or her representative shall inspect and supervise the actual pouring of any concrete governed by this chapter.
(Ord. 95-86. Passed 2-17-87.)
(f) This section is also effective with respect to concrete which is poured to replace a previously existing hard surface driveway or sidewalk.
(Ord. 177-94. Passed 6-6-94.)