10-3-5: NOTICE FOR INSPECTION REQUIRED:
The owner or contractor shall give twenty four (24) hours' advance notice to the director of community development:
   A.   Before concrete is poured and after footing excavation has been completed.
   B.   Before backfilling and after footing drain tile has been placed and foundation wall has been waterproofed.
   C.   After foundation has been poured and prior to framing, an on site location and top of foundation elevation, prepared by a registered land surveyor, is to be submitted to the director of community development.
   D.   At the time of water connection and before backfilling the water service.
   E.   Before any interior wall finish is applied and after the framing is completed.
   F.   Before any interior wall finish is applied and after the rough plumbing is completed.
   G.   Before any interior wall finish is applied and after rough electrical installation is completed.
   H.   Before any siding or brick veneer or shingles are applied and after the application of the sheathing paper.
   I.   Before any backfilling and after the septic tank and seepage system have been installed.
   J.   Before final inspection. (Ord. G-160, 6-11-1974)