1-14-1: FEES ESTABLISHED:
The following fees are hereby established and shall be payable upon submission of an application, except as otherwise specifically noted herein, for the following:
   A.   Application for amendment under the zoning ordinance   $750.00
   In addition to the above fees, all applicants shall reimburse the village for the publication cost of the public notice within thirty (30) days of the date the village seeks reimbursement for such charges.
   B.   Application for special use permit:
      Zoning ordinance   $750.00
   In addition to the above fees, all applicants shall reimburse the village for the publication cost of the public notice and shall reimburse the village for any outside consulting review charges within thirty (30) days of the date the village seeks reimbursement for such charges.
   C.   Application for variation under the zoning ordinance or the storm water regulations   $750.00
   In addition to the above fees, all applicants shall reimburse the village for the publication cost of the public notice and shall reimburse the village for any outside consulting review charges within thirty (30) days of the date the village seeks reimbursement for such charges.
   D.   Application for appeal under the zoning ordinance or the storm water regulations   $300.00
   In addition to the above fees, all applicants shall reimburse the village for any outside consulting review charges within thirty (30) days of the date the village seeks reimbursement for such charges.
   E.   Application for subdivision:
      1.   Preliminary plat, per lot   $ 50.00
         Minimum fee   750.00
      2.   Final plat   750.00
      3.   Plans and specifications: The following fees for the review of engineering plans and specifications shall be paid to the village at the time the documents are submitted for review:
 
Estimated Cost Of Construction Of Land Improvements
Basic Minimum Fee (As A Percentage Of Estimated Cost)
Less than $10,000.00
$275.00
$10,001.00 to $20,000.00
3.00%
$20,001.00 to $50,000.00
2.50%
$50,001.00 to $100,000.00
2.25%
$100,001.00 and over
2.00%
 
   In addition to the above fees, all applicants shall reimburse the village for any outside consulting review charges within thirty (30) days of the date the village seeks reimbursement for such charges.
      4.   Engineering inspection: At the time the subdivision plat is presented for final approval, a fee for inspection of the improvement shall be paid to the village in the amount indicated by the following table:
 
Estimated Cost Of Construction Of Land Improvements
Fee (As A Percentage Of Estimated Cost)
Less than $10,000.00
$250.00
$10,001.00 to $20,000.00
2.25%
$20,001.00 to $50,000.00
2.00%
$50,001.00 and over
1.50%
 
   The above fees shall be for the periodic inspection of the improvements. In addition to the above fees, all applicants shall reimburse the village for any outside consulting inspection charges within thirty (30) days of the date the village seeks reimbursement for such charges.
      5.   Resubmissions: Upon resubmission of any final plat which has not been recorded because of noncompliance with the provisions of section 14-4-8 of this code, the fees enumerated under subsections E2, E3 and E4 of this section shall be paid, notwithstanding any prior payment.
F.
Application for amendment or variation to the subdivision regulations
$750.00
 
In addition to the above fees, all applicants shall reimburse the village for the publication cost of the public notice within thirty (30) days of the date the village seeks reimbursement for such charges.
G.
Application for certificate of appropriateness in the historic Graue Mill Gateway area.
$ 500.00
H.
Application for time extension: preliminary and final subdivision plat, special use, and variation.
125.00
I.
Application for planned developments under the zoning ordinance:
 
 
1.
New planned development or major change to an existing planned development base fee:
1,500.00
 
 
Plus for each waiver or variation to this code
500.00
 
 
Plus all applicable third party costs and recoverable expenses.
 
 
2.
Minor change to an approved planned development
750.00
 
 
Plus for each waiver or variation to this code
500.00
 
 
Plus all applicable third party costs and recoverable expenses.
 
 
3.
Initial escrow deposit:
 
 
 
From which anticipated third party costs and recoverable expenses are to be drawn. No interest shall be payable on any such escrow account.
500.00
 