9-5-3: POSTCONSTRUCTION BEST MANAGEMENT PRACTICE SUBMITTAL:
The postconstruction best management practice (PCBMP) submittal shall include:
   A.   A discussion documenting compliance with the requirements of chapter 8 of this title.
   B.   A listing and discussion of all PCBMPs to be used.
   C.   Supporting calculations documenting compliance with the volume reduction BMP requirements.
   D.   For manufactured PCBMPs, the manufacturer documentation to support pollutant removal rates shall be supplied.
   E.   A BMP specific planting/seeding plan for all areas to be vegetated which shall include:
      1.   Identified locations for all plantings (e.g., lawn, upland prairie, wet prairie, etc.), seeding and planting specifications and methodology; and
      2.   A schedule for installation; and
      3.   Proposed maintenance and monitoring provisions; and
      4.   An opinion of probable cost to construct the BMPs. (Ord. G-976, 7-24-2012; Ord. G-1003, 6-11-2013)