1481.01 INTRODUCTION; PURPOSES; GENERAL PROVISIONS.
   (a)   The prevention of accelerated flooding and stream channel erosion in conjunction with urban development requires control of the discharge rate and volume of runoff prior to its release to off-site land. The purposes of this chapter are to permit development without increasing the flooding of other lands and to provide a basis for the design of storm drainage systems on lands above or below undeveloped areas, which design will preserve the rights and options of both contributing and receiving property owners and ensure the long term adequacy of storm drainage systems.
   (b)   Accelerated channel erosion as well as increased flooding damage could be controlled if the predevelopment hydrograph could be maintained. It is usually not practical, however, to retain the predevelopment rate of infiltration when a large part of the watershed is covered with impervious surfaces. The concept of reducing peak flows below those of predevelopment storms was developed as an alternative to maintaining the predevelopment hydrograph. The logic of this concept is to compensate for the increased erosiveness of:
      (1)   Increased volume of runoff due to less infiltration;
      (2)   More frequent occurrences of the same flow. For example, a subdivision may have the peak flow of a predevelopment five-year storm occur once a year after development is complete.
      (3)   Less sediment in the runoff water because the watershed is paved with nonerosive surfaces or good grass cover.
   (c)   The two-step standard requires that:
      (1)   The peak rates of runoff from an area after development shall be not greater than the peak rates of runoff from the same area before development for all twenty-four hour storms from one to 100-year frequency. Designing for the one, two, five, ten, twenty-five, fifty and 100-year storms is considered adequate to meet the requirement. Storm water requirements must be met at each point storm water is discharged from a development area.
      (2)   If the volume of runoff from an area after development will be greater than the volume of runoff from the same area before development, it shall be compensated by reducing the peak rate of runoff from the critical storm and all more frequent storms occurring on the development area to the peak rate of runoff from a one-year frequency, twenty-four hour storm occurring on the same area under predevelopment conditions. Storms of less frequent occurrence (longer return periods) than the critical storm up to the 100-year storm shall have peak runoff rates not greater than the peak runoff rates from equivalent size storms under predevelopment conditions.
   (d)   The critical storm for a specific development area is determined as follows:
      (1)   Determine the total volume of runoff from a one-year frequency, twenty-four hour storm occurring on the development area before and after development; and
      (2)   From the volumes determined in paragraph (d)(1) hereof, determine the percent of increase in volume of runoff due to development, and using this percentage, select the twenty-four hour critical storm from the following table:
   If the percentage of increase
   in volume runoff is:                        The twenty-four hour critical
   Equal to or and less                     storm for discharge limitation
   greater than than                        will be:
   0      10                      1 year
   10      20                      2 year
   20      50                      5 year
   50      100                     10 year
   100      250                     25 year
   250      500                     50 year
   500       --                     100 year
      This standard basically requires peak flow to be reduced in proportion to increased runoff volume. If runoff volume is not increased, peak flows are only required to match predevelopment peak runoff rates for equivalent size storms for all storms from one-year to 100-year storms. This criteria is designed to require more control when the change in the runoff pattern caused by development is more drastic. The quantity and cost of preventative control features will need to be in proportion to the level of increase in runoff caused by the change in land use, a fair and equitable criterion.
   (e)   Concern is frequently expressed in regard to the extremes of the accelerated storm water control standard, the one and 100-year frequency storms. Justification for using the one-year storm is based on the erosivity of stream flow and on what is known as the routing problem. Small or frequent storms are very erosive simply because they occur so often. Damage doesn't have time to heal before the next storm comes. Bankfull channel flow is essentially the most erodible state of stream flow on the channel itself. Any increase spills out over the flood plain with very little increase in the velocity of channel flow. Any flow less than bankfull generally has a corresponding decrease in velocity, and therefore, less erosion damage to the channel. Where there is a significant increase in runoff volume, it is very important to have the runoff occur at something less than bankfull flow, especially in watersheds approaching complete development. Longer duration of bankfull flow than that which occurred under predevelopment conditions, can have disastrous effects on the stream channel and resulting sediment pollution. Since channels generally size themselves for about one and one-half to a two-year frequency storm runoff event, the one-year storm was chosen as the control storm to prevent significant channel erosion.
   (f)   The routing problem is the problem of channel flow downstream from numerous smaller watersheds. As runoff from the smaller watersheds is altered, the effect on channel flow somewhere downstream where all of the watersheds come together can be favorable or adverse. Ideally, the entire large watershed should be hydraulically planned and the level of control of each sub-watershed should be based on the accumulative effects downstream. Since experience has proven the near impossibility, politically, of realizing that degree of organizational control, the one-year outlet rate is further justified in order to minimize adverse effects on the routing problem when compensation is necessary to control increased flow volumes.
   (g)   Many people suppose that runoff peaks and volumes do not increase from the large or infrequent storm because the ground is saturated by these storms and most of the rainfall will run off, whether the land is used for forest land, crop land or urban purposes. Urbanization can, in fact, cause an increase in both peak and volume of runoff. Most of the increase may be in the early part of such a storm, and perhaps the twenty-five or fifty-year storm control may adequately address the situation. There are many variables which affect the storm water runoff pattern – soil type, slope, kind of cover, percentage of impervious cover, kind of disturbance and compaction. The 100-year storm needs to be examined in a development situation to determine its specific effect. Emergency flow areas and emergency outlets from structural work need to account for such storms if we don't want basements full of water and structures failing. The additional control necessary for the 100-year frequency storm is not a highly significant factor in storm water management for accelerated runoff control.
   (h)   In addition to controlling channel erosion, this standard should make long range planning for storm water management easier. Storm sewers and stream channels can be designed in accordance with existing runoff conditions knowing that upstream runoff rates cannot be increased. This standard would also prevent an increase in flood levels and frequencies below future developments and, in many cases, reduce development costs because of reduced storm sewer size, particularly where multiple use detention facilities can be utilized in designated open space.
   (i) A uniform standard for determining runoff would be helpful in designing to meet this standard. We are requiring the U.S. Soil Conservation Service procedures in Technical Release No. 55, 1986 edition or latest edition, which consider watershed area, watershed shape, change in land use, soil type, hydrologic condition, impervious area, modification of hydraulic channels, increased intensity of rainfall near the middle of a storm, initial abstraction (surface storage, interception and infiltration prior to runoff) and decreased infiltration as a storm progresses.
   All procedures of SCS Technical Release No. 55 shall be followed with the below described modification:
           STORM                      24-HOUR RAINFALL
      FREQUENCY                        VALUES (P)*
      1-YEAR                        2.04
      2-YEAR                        2.50
      5-YEAR                        3.10
       10-YEAR                        3.60
       25-YEAR                        4.39
       50-YEAR                        5.11
       100-YEAR                        5.89
* Rainfall Distribution from Rainfall Frequency Atlas of the Midwest, Bulletin 71 published in 1992 and authored by Huff and Angel.
(Ord. 05-79. Passed 6-7-05.)