(A) Pursuant to authority granted by I.C. 36-4-6-18, the Sewer Board will submit an annual itemized budget for review to the Common Council no later than July 15 of each calendar year. All operational and project expenses will be included in presented budget.
(B) Pursuant to authority granted by I.C. 36-4-6-18 the Sewer Board will prepare and present detailed plans and preparations to the Common Council for planned sewer project work to be initiated and completed inside the county 30 days before start up. All emergency projects and costs will be reported to the Council meeting immediately following the emergency. Contractor selection and finalized construction cost will be included in reports.
(C) Pursuant to I.C. 36-4-6-21 the Sewer Board will provide bi-annual documented progress reports to the Common Council regarding agreements with the Environmental Protection Agency (EPA) and all amended "consent" regulation. These reports will be presented to the Common Council on July 15 and December 15 respectively.
(Ord. G-06-39, passed 9-21-2006)