15.702: INSPECTION PROCEDURES:
   A.   Preconstruction Meeting: Prior to commencing the construction and installation of any development, site improvement or maintenance work contemplated herein to be constructed or installed, the applicant's contractors shall meet with the village engineer, the director of community development and the director of public works to review the inspection methods and procedures outlined herein for each construction and installation.
   B.   Inspections: All developments, site improvements, or maintenance work constructed under the terms of this chapter shall be subject to inspections by the director of public works and/or the director of community development. The applicant shall give at least forty eight (48) hours' notification to the director of public works and/or the director of community development prior to the performance of any work.
   C.   Procedures: Within the forty eight (48) hours' notice period specified in subsection B of this section, the public works director and/or the director of community development may conduct an on site inspection to determine that the work complies with the engineering drawings.
      1.   If such work does not comply with the final drawings, the director of public works and/or the director of community development shall have the authority to order that all such work shall be terminated until such time as necessary steps are taken by the applicant to correct any defects or deficiencies.
      2.   After the required corrections have been completed, the applicant shall again notify the director of public works and/or the director of community development as provided in subsection B of this section.
   D.   Final Inspection: Upon completion of all work covered by the building permit, the applicant shall notify the director of public works and/or the director of community development, who shall thereupon authorize a final inspection of all improvements so installed.
      1.   If such final inspection indicates that there are any defects or deficiencies in any such improvement as installed, or if there are any deviations in such improvements, as installed, from the final engineering drawings; which defects will, in the opinion of the director of public works and/or the director of community development adversely affect the performance, suitability, or desirability of said improvements, the director of public works and/or the director of community development shall notify the applicant in writing of such defects, deficiencies, or deviations and the applicant shall correct such defects or deviations within sixty (60) days of the date of notification. All corrective measures shall be made at the applicant's sole cost and expense.
      2.   When such defects, deficiencies or deviations have been corrected, the applicant shall notify the director of public works and/or the director of community development that the improvements are ready for final inspection.
      3.   The fees for the final inspection of all improvements, plus one follow up inspection are included in the fees for the permit. If deficiencies in the design, construction, and/or restoration remain after the follow up inspection, additional follow up inspections will be required. In such cases, reinspection fees shall be assessed in an amount as set forth in appendix A, division II of this code. (Ord. 5253, 5-21-2002)