§ 8.09.060 REVIEW OF WMP.
   (A)   (1)   Notwithstanding any other provision of this code, no building or demolition permit shall be issued for any covered project unless and until the City Solid Waste Program Administrator has approved the WMP.
      (2)   Approval shall not be required, however, where an emergency demolition is required to protect public health or safety.
   (B)   The Solid Waste Program Administrator shall only approve a WMP if he or she first determines that all of the following conditions have been met:
      (1)   The WMP provides all of the information set forth in § 8.09.030;
      (2)   The WMP indicates that the diversion requirement will be met; and
      (3)   The applicant has submitted an appropriate performance security in compliance with § 8.09.040.
   (C)   If the Solid Waste Program Administrator determines that these three conditions have been met, he or she shall mark the WMP “Approved,” return a copy of the WMP to the applicant, and notify the Building Department that the WMP has been approved.
   (D)   If the Solid Waste Program Administrator determines that the WMP is incomplete or fails to indicate that the diversion requirement will be met, he or she shall either:
      (1)   Return the WMP to the applicant marked “Denied,” including a statement of reasons, and so notify the Building Department, which shall then immediately stop processing the building or demolition permit application; or
      (2)   Return the WMP to the applicant marked “Further Explanation Required,” with a statement of the issues that require additional clarification or explanation.
   (E)   The Solid Waste Program Administrator shall complete the review of a WMP, and either approve or disapprove the WMP or find the WMP incomplete within three working days after the WMP has been submitted.
(Ord. 2003-08 § 2 (part), 2003)