(A) Applicants for building or demolition permits involving any covered project shall complete and submit a Waste Management Plan (“WMP”) on a WMP form approved by the city for this purpose as part of the application packet for the building or demolition permit. The completed WMP shall indicate all of the following:
(1) The project location, the name and address of the applicant, and the project contact person;
(2) The estimated volume or weight of project C&D debris to be generated;
(3) The percentage of C&D debris that can feasibly be diverted via reuse or recycling;
(4) The vendors or facilities that the applicant proposes to use to collect or receive the C&D debris that will be reused or recycled;
(5) The disposal facility that will be used for C&D debris that cannot be recycled or reused; and
(6) The amount and form of the performance security for the project.
(B) To estimate the volume or weight of C&D debris identified in the WMP, the applicant shall use the Standardized Generation Rates Table approved by the City Manager for this purpose.
(C) The WMP for a project must be reviewed and approved by the City Solid Waste Program Administrator prior to the issuance of a building or demolition permit for the project.
(D) If an applicant believes that a covered project will not generate any recyclable materials, the applicant may include such a statement in the WMP and apply for an exemption from the diversion requirement pursuant to § 8.09.080.
(Ord. 2003-08 § 2 (part), 2003)