(a) No land development activity requiring review and approval under this Division shall be initiated without having first received such review and approval.
(b) Review procedures differ depending upon the type of proposal. Generally, the procedures for all applications have three common elements: (1) submittal of a complete application, including required fee payment along with appropriate information; (2) review of the submittal by appropriate City staff and related agencies; and (3) action to approve, approve with conditions, or deny the application. Submittal dates and review time periods are established as part of the administrative policies and supplemental procedures of the City, copies of which may be obtained from the zoning administrator.
(c) Table 35-2100.1. summarizes the procedures, agencies and personnel involved in the administrative development review process. Detailed information about the general procedures and applications and the agencies and public bodies involved in the process, and methods of appeal, are further discussed in Sec. 35-2101.
Application Process | Pre-app. Conf. | Acting Body |
Application Process | Pre-app. Conf. | Acting Body | ||||||
ZA | BO | CE | BBA | PC | CC | ZHO | ||
Zoning Certificate | Optional | DM | - | - | - | - | - | A |
Building Permit | Optional | RB | DM | - | A | - | - | |
Certificate of Occupancy | Optional | RB | DM | - | A | - | - | A |
Site Plan Review | Mandatory | DM | - | - | - | A | - | - |
Zoning Compliance Letter | Mandatory | DM | - | - | - | - | - | A |
Administrative Variance | Optional | DM | - | - | - | - | - | A |
Minor Subdivision | Mandatory | DM[1] | - | RB | - | A | - | - |
Improvement Plan | Optional | - | - | DM | - | - | - | - |
Final Subdivision Plat (No Dedication) | Optional | DM[2] | - | RB | - | A | DM[2] | -
|
Table Legend:
A = Appeal Body | CC = City Council | DM = Decision-Making Body |
BO = Building Official | PC = Plan Commission | RB = Review Body |
ZA = Zoning Administrator | ZHO = Zoning Hearing Officer | - = Not applicable |
CE = City Engineer | BBA = Building Board of Appeals | |
[1]The zoning administrator is authorized to defer decision-making authority to the plan commission. If the zoning administrator defers decision-making authority to the plan commission, the City Council becomes the appeal body. [2] Only the City Council is authorized to take action on final plats that propose the dedication of land or improvements to the City.
|