8-1-12: PLAN REVIEW, CONSTRUCTION, AND INSPECTION FEES REQUIRED:
   Building permit fees consisting of plan review fees, construction/inspection fees applicable to all construction within the village shall be paid prior to receiving a permit. Building permit fees in subsection A of this section are all-inclusive for those project types listed. All other projects shall have total permit fees calculated by sum of all required fees in subsections B through G of this section. The following fees are hereby established and adopted:
   A.   All-inclusive permit fees.
      1.   Fixed-Fee Permits and No-Fee Permits.
               Table 8-1-12.A.1
Permit Type
Number and Type of Required Inspections
Fee1,2,3,4
Permit Type
Number and Type of Required Inspections
Fee1,2,3,4
Asphalt Paving (re-paving of parking lots, driveways)
2 (base, final striping)
$70.00
Concrete Flatwork or Pavers (including driveways, sidewalks, patios, sports courts, stoops, steps)
2 (pre-pour, final)
$70.00
Construction Trailer
1 (final)
$70.00
Deck with 2 inspections - (decks where floor framing will be visible at time of final inspection)
2 (post holes, final)
$70.00
Deck with 3 inspections - (decks where floor framing will NOT be visible at time of final inspection)
3 (post holes, rough, final)
$90.00
Demolition (commercial)
1 (final)
$90.00
Demolition (residential and accessory structure)
1 (final)
$70.00
Driveways - see Concrete Flatwork
-
-
Dumpster
No Inspections
No Fee
Electrical Vehicle Chargers (residential)
1 (final electrical)
$70.00
Electrical Vehicle Chargers (commercial)
2 (underground & final electrical)
$110.00
Fence
1 (post holes)
1 (final only w/ pool)
$70.00
Gazebos - Prefabricated (detached structures, less than or equal to 200 sq. ft. in size)
1 (final)
$70.00
Gazebos - Prefabricated (detached structures, 200 to 400 sq. ft. in size)
2 (post holes, final)
$90.00
Gazebos - Larger than 400 sq. ft., or Site-Built or attached to building
Varies
$6.50 per $1,000 of Cost of Construction (See Sections 8-1-12.B & 8-1-12.C)
Generator (residential)
2 (final electric & mechanical)
$90.00
Generator (commercial)
2 (final electric & mechanical)
$110.00
Lawn Sprinkler System
1 (final plumbing)
$70.00
Mechanical Unit Replacement with same (residential)
No Inspections
No Fee
Mechanical Unit New (residential)
1 (final mechanical)
$70.00
Mechanical Unit New or Replacement (commercial)
1 (final mechanical)
$90.00
Re-roof (residential and commercial sloped)
No Inspections
No Fee
Re-roof (commercial flat roof)
Varies
$7.00 per $1,000 of Cost of Construction (See Sections 8-1-12.B & 8-1-12.C)
Shed
2 (base pre-pour, final)
$70.00
Siding replacement (residential)
No Inspections
No Fee
Solar Panels / PV Array (residential)
1 (final electric)
$90.00
Tents (commercial, 400 sq. ft. or smaller)
No Inspections
No Fee
Tents (commercial, 401 sq. ft. and larger)
2 (electrical, final)
$90.00
Tree Removal or Pruning in R.O.W.
1 (final)
No Fee
Water Heater Replacement (residential)
No Inspections
No Fee
Water Heater replacement (commercial)
1 (final plumbing)
$90.00
Windows or Door replacement
 
(without changes to rough opening)
No Inspections
No Fee
Windows or Door with new opening
1 (rough framing)
$70.00
 
Note:
1.   Fixed Fee Permits fees are inclusive of the required plan review, zoning review, construction and inspection fees for properties zoned residential. Fixed Fee Permits for commercially zoned properties may require additional reviews and approvals.
2.   Additional re-reviews or re-inspections fees are applicable per Table 8-1-12.B.7, and Table 8-1-12.C.1.
3.   Types of projects not explicitly listed above or projects which exceed the scope of work generally associated with permits listed above, shall at the Building Official’s discretion, have total permit fees calculated by sum of all required fees in subsections B through G of this section.
4.   No-fee Permits listed above, while still requiring a permit, are not charged any permit fees and do not require any inspections, unless indicated otherwise by the Building Official. All contractors listed on no-fee permits must be licensed in accordance with Title 3, Chapter 8 of the Village Code.
(Ord. 2007-O-036, 8-13-2007; amd. Ord. 2014-O-031, 8-25-2014; Ord. 2024-O-001, 1-8-2024; Ord. 2024-O-014, 4-22-2024)