10-2-3: EXPIRATION OF BUILDING PERMIT:
   Section 105.3.2 Time Limit of application Change all reference to 180 days to 30 days:
   Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within one hundred eighty (180) days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of one hundred eighty (180) days after the time the work is commenced. The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than one hundred eighty (180) days each. The extension shall be requested in writing and justifiable cause demonstrated.
(Ord. 1570, 9-17-2012; amd. Ord. 1776, 11-6-2023)