1379.04 USE AND DEVELOPMENT STANDARDS FOR FLOOD HAZARD REDUCTION.
   The following use and development standards apply to development wholly within, partially within, or in contact with any special flood hazard area as established in Section 1379.01(f).
   (a)   Use Regulations.
      (1)   Permitted Uses. All uses not otherwise prohibited in this section or any other applicable land use regulation adopted by City of Medina are allowed provided they meet the provisions of these regulations.
      (2)   Prohibited Uses.
         A.   Private water supply systems in all special flood hazard areas identified by FEMA, permitted under Section 3701 of the Ohio Revised Code.
         B.   Infectious waste treatment facilities in all special flood hazard areas, permitted under Section 3734 of the Ohio Revised Code.
         C.   Storage or processing of materials identified in all groups listen under Hazardous Group "H" as defined in the State of Ohio Commercial Building Code,
         D.   Facilities with on-site bulk storage of gasoline and/or diesel fuel.
         E.   Storage of material or equipment which, in time of flooding, could be come buoyant and pose an obstruction to flow,
   (b)   Water and Wastewater Systems. The following standards apply to all water supply, sanitary sewerage and waste disposal systems not otherwise regulated by the Ohio Revised Code:
      (1)   All new and replacement water supply systems shall be designed to minimize or eliminate infiltration of floodwaters into the systems;
      (2)   New and replacement sanitary sewerage systems shall be designed to minimize or eliminate infiltration of flood waters into the systems and discharge from the systems into flood waters; and,
      (3)   On-site waste disposal systems shall be located to avoid impairment to or contamination from them during flooding.
   (c)   Subdivisions and Large Developments. 
      (1)   All subdivision proposals shall be consistent with the need to minimize flood damage and are subject to all applicable standards in these regulations;
      (2)   All subdivision proposals shall have public utilities and facilities such as sewer, gas, electrical, and water systems located and constructed to minimize flood damage;
      (3)   All subdivision proposals shall have adequate drainage provided to reduce exposure to flood damage; and
      (4)   In all areas of special flood hazard where base flood elevation data are not available, the applicant shall provide a hydrologic and hydraulic engineering analysis that generates base flood elevations for all subdivision proposals and other proposed developments containing at least 50 lots or 5 acres, whichever is less.
      (5)   The applicant shall meet the requirement to submit technical data to FEMA in Section 1379.03(h)(1)A.4. when a hydrologic and hydraulic analysis is completed that generates base flood elevations as required by subsection (c)(4) hereof.
   (d)   Residential Structures.
      (1)   New construction and substantial improvements shall be anchored to prevent flotation, collapse, or lateral movement of the structure resulting from hydrodynamic and hydrostatic loads, including the effects of buoyancy.
      (2)   New construction and substantial improvements shall be constructed with methods and materials resistant to flood damage.
      (3)   Where a structure, including its foundation members, is elevated on fill to or above the base flood elevation, the requirements for anchoring and construction materials resistant to flood damage are satisfied.
      (4)   New construction and substantial improvements shall be constructed with electrical, heating, ventilation, plumbing and air conditioning equipment and other service facilities that are designed and/or elevated so as to prevent water from entering or accumulating within the components during conditions of flooding.
      (5)   New construction and substantial improvement of any residential structure, including manufactured homes, shall have the lowest floor, including basement, elevated to or above the flood protection elevation (See Section 1379.02 "Definitions"). Where flood protection elevation data are not available the structure shall have the lowest floor, including basement, elevated at least two feet above the highest adjacent natural grade.
      (6)   New construction and substantial improvements, including manufactured homes, that do not have basements and that are elevated to the flood protection elevation using pilings, columns, posts, or solid foundation perimeter walls with openings sufficient to allow unimpeded movement of flood waters may have an enclosure below the lowest floor provided the enclosure is used only for the parking of vehicles, building access, or storage and meets the following standards:
         A.   Be designed and certified by a registered professional engineer or architect to automatically equalize hydrostatic flood forces on exterior walls by allowing for the entry and exit of floodwaters; or
         B.   Have a minimum of two openings on different walls having a total net area not less than one square inch for every square foot of enclosed area, and the bottom of all such openings being no higher than one foot above adjacent exterior grade. The openings may be equipped with screens, louvers, or other coverings or devices provided that they permit the automatic entry and exit of floodwaters.
      (7)   Manufactured homes shall be affixed to a permanent foundation and anchored to prevent flotation, collapse or lateral movement of the structure resulting from hydrodynamic and hydrostatic loads, including the effects of buoyancy. Methods of anchoring may include, but are not limited to, use of over-the-top or frame ties to ground anchors.
      (8)   Repair or rehabilitation of historic structures upon a determination that the proposed repair or rehabilitation will not preclude the structure's continued designation as a historic structure and is the minimum necessary to preserve the historic character and design of the structure, shall be exempt from the development standards of subsection (d) hereof.
   (e)   Nonresidential Structures.   
      (1)   New construction and substantial improvement of any commercial, industrial or other nonresidential structure shall meet the requirements of subsection (d)(1)-(3) and (5)-(8).
      (2)   New construction and substantial improvement of any commercial, industrial or other nonresidential structure shall either have the lowest floor including basement, elevated to or above the level of the flood protection elevation; or, together with attendant utility and sanitary facilities, shall meet all of the following standards:
         A.   Be dry floodproofed so that the structure is watertight with walls substantially impermeable to the passage of water to the level of the flood protection elevation;
         B.   Have structural components capable of resisting hydrostatic and hydrodynamic loads and effects of buoyancy; and,
         C.   Be certified by a registered professional engineer or architect, through the use of a Federal Emergency Management Agency Floodproofing Certificate, that the design and methods of construction are in accordance with subsection (e)(2)A. and B.
      (3)   Where flood protection elevation data are not available the structure shall have the lowest floor, including basement, elevated at least two feet above the highest adjacent natural grade.
   (f)   Accessory Structures. Relief to the elevation or dry floodproofing standards may be granted for accessory structures containing no more than 600 square feet. Such structures must meet the following standards:
      (1)   They shall not he used for human habitation;
      (2)   They shall be constructed of flood resistant materials;
      (3)   They shall be constructed and placed on the lot to offer the minimum resistance to the flow of floodwaters;
      (4)   They shall be firmly anchored to prevent flotation;
      (5)   Service facilities such as electrical and heating equipment shall be elevated or floodproofed to or above the level of the flood protection elevation; and
      (6)   They shall meet the opening requirements of subsection (d)(6) hereof;
   (g)   Recreational Vehicles. Recreational vehicles must meet at least one of the following standards:
      (1)   They shall not be located on sites in special flood hazard areas for more than 180 days, or
      (2)   They must be fully licensed and ready for highway use, or
      (3)   They must meet all standards of subsection (d) hereof.
   (h)   Above Ground Gas or Liquid Storage Tanks. All above ground gas or liquid storage tanks shall be anchored to prevent flotation or lateral movement resulting from hydrodynamic and hydrostatic loads.
   (i)   Storage of Materials. Material or equipment stored within the Special Flood Hazard Area shall be located outside of the identified floodway area and be firmly anchored to prevent flotation.
   (j)   Critical Development Protection. The lowest floor of Critical Developments (See Section 1379.02 "Definitions"), including the bottom of underground gas/oil/propane storage tanks, shall be elevated to a minimum of two (2) feet higher than: the 500-year flood elevation or the highest known historical flood elevation (where records are available), whichever is greater. If no data exists establishing the 500-year flood elevation or the highest known historical flood elevation, the applicant shall provide a hydrologic and hydraulic engineering analysis that generates the 500-year flood elevation data.
   (k)   Access. Proposed roads in Special Flood Hazard Areas within new subdivision developments shall be designed and constructed so that the road surface is elevated to or above the Base Flood Elevation.
   (l)   Compensatory Storage. Development within the Special Flood Hazard Area shall result in no net loss of natural floodplain storage. The volume of the loss of floodwater storage due to development shall be offset by providing an equal or greater volume of permanent flood storage by excavation or other compensatory measures at or adjacent to the development site. This compensatory floodplain storage shall be proposed and created in accordance with the following requirements:
      (1)   Prior to issuance of a Stormwater Management Permit, a plan and calculations prepared by a professional engineer shall be submitted for approval. This plan shall be based on a field survey, shall show the existing and proposed grades of the development and compensatory storage areas, and shall be accompanied by calculations which demonstrate that the proposed stage vs. storage volume relationship of the compensatory storage area would have the same or greater storage volume at each stage as in the pre-development condition of the proposed development area.
      (2)   The compensatory storage area shall have a hydraulic connection to the affected watercourse which is equal to or greater than the pre-development conditions and shall provide the same or improved rate of flood storage capture and discharge over the course of the flood event as in the pre-development conditions.
      (3)   Compensatory storage shall be located adjacent to the development area or on the opposite side of the stream across from the development area. In the case of filling for a new stream crossing, the compensatory storage shall be located upstream of the crossing.
      (4)   The compensatory storage area shall be a permanent component of the property, and shall be repaired or replaced by the owner of the property if silted-in or otherwise compromised by activities other than natural movement of the stream.
      (5)   Where the applicant proposes compensatory storage on property owned by others, the applicant shall submit a written agreement between such landowner and the applicant wherein the landowner agrees to convey an easement or other property interest or right to the applicant allowing compensatory storage, and to permanently maintain such area for flood storage purposes, as described in (4), above. Prior to construction, the applicant shall submit documentation showing that conveyance of easements, property interests or rights have been properly recorded with the Medina County Recorder's Office,
      (6)   The design and creation of the development and compensatory storage areas shall incorporate best management practices as required by other Medina County regulations or state or federal agencies to minimize soil erosion and sediment impacts.
      (7)   Prior to grading or construction in development and compensatory storage areas, the applicant shall be responsible for obtaining any necessary permits or approvals from other involved agencies such as the Army Corps of Engineers and the Ohio EPA.
      (8)   Prior to grading or construction in development and compensatory storage areas, the applicant may be required to submit technical data regarding the proposed flood boundary revision to FEMA and obtain a Conditional Letter of Map Revision (CLOMR) in accordance with Section 1379.03(h)(1) of these regulations, based on the determination by the Floodplain Administrator.
      (9)   After the development and compensatory storage areas are complete, an as-built topographic survey of the development area and the compensatory storage area shall be prepared and stamped by a professional surveyor and submitted to the Floodplain Administrator. This survey shall be accompanied by as-built stage vs. storage volume calculations prepared by a professional engineer as described in (1.), above.
      (10)   After the development and compensatory storage areas are satisfactorily complete, the applicant shall submit technical data to and obtain a Letter of Map Revision from FEMA in accordance with Section 1379.03(h)(1) of these regulations. When the development and compensatory storage areas are created for a new subdivision development, the Letter of Map Revision shall be obtained prior to the Medina County Engineer's approval of the final subdivision plat.
These regulations regarding compensatory storage shall not apply to public highway, transportation, or drainage improvements or maintenance thereof undertaken by a government agency or political subdivision.
   (m)   Assurance of Flood Carrying Capacity. Pursuant to the purpose and methods of reducing flood damage stated in these regulations, the following additional standards are adopted to assure that the reduction of the flood carrying capacity of watercourses is minimized:
      (1)   Development in Floodways. In floodway areas, development shall cause no increase in flood levels during the occurrence of the base flood discharge. Prior to issuance of a floodplain development permit, the applicant must submit a hydrologic and hydraulic analysis, conducted by a registered professional engineer, demonstrating that the proposed development would not result in any increase in the base flood elevation.
      (2)   Development in Riverine Areas with Base Flood Elevations but No Floodways.   
         A.   In riverine special flood hazard areas identified by FEMA where base flood elevation data are provided but no floodways have been designated, the cumulative effect of any proposed development, when combined with all other existing and anticipated development, shall not increase the base flood elevation more than 1.0 (one) foot at any point. Prior to issuance of a floodplain development permit, the applicant must submit a hydrologic and hydraulic analysis, conducted by a registered professional engineer, demonstrating that this standard has been met; or,
         B.   Development in riverine special flood hazard areas identified by FEMA where base flood elevation data are provided but no floodways have been designated causing more than one foot increase in the base flood elevation may be permitted provided all of the following are completed by the applicant:
            1.   An evaluation of alternatives which would result in an increase of one foot or less of the base flood elevation and an explanation why these alternatives are not feasible;
            2.   Meet the requirements to submit technical data in Section 1379.03(h)(1);
            3.   Certification that no structures are located in areas that would be impacted by the increase in base flood elevation;
            4.   Documentation of individual legal notices to all impacted property owners within and outside the community, explaining the impact of the proposed action on their property; and
            5.   Concurrence of the Mayor of City of Medina and the Chief Executive Officer of any other communities impacted by the proposed actions.
      (3)   Alterations of a Watercourse. For the purpose of these regulations, a watercourse is altered when any change occurs within its banks. The extent of the banks shall be established by a field determination of the “bankfull stage”. The field determination of "bankfull stage” shall be based on methods presented in Chapter 7 of the USDA Forest Service General Technical Report RM-245, Stream Channel Reference Sites: An Illustrated Guide to Field Technique or other applicable publication available from a Federal, State, or other authoritative source. For all proposed developments that alter a watercourse, the following standards apply:
         A.   The bankfull flood carrying capacity of the altered or relocated portion of the watercourse shall not be diminished. Prior to the issuance of a floodplain development permit, the applicant must submit a description of the extent to which any watercourse will be altered or relocated as a result of the proposed development, and certification by a registered professional engineer that the bankfull flood carrying capacity of the watercourse will not be diminished.
         B.   Adjacent communities, the U.S. Army Corps of Engineers, and the Ohio Department of Natural Resources, Division of Water, must be notified prior to any alteration or relocation of a watercourse. Evidence of such notification must be submitted to the Federal Emergency Management Agency.
         C.   The applicant shall be responsible for providing the necessary maintenance for the altered or relocated portion of said watercourse so that the flood carrying capacity will not be diminished. The Floodplain Administrator may require the permit holder to enter into an agreement with City of Medina specifying the maintenance responsibilities. If an agreement is required, it shall be made a condition of the floodplain development permit.
         D.   The applicant shall meet the requirements to submit technical data in Section 1379.03(h)(1)A.3., when an alteration of a watercourse results in the relocation or elimination of the special flood hazard area, including the placement of culverts.
         E.   Alteration of watercourses which are tributary to a watercourse which is the main stem or cause of a special flood hazard area are subject to the requirements of subsection (m)(3) hereof if such alteration is situated within a floodway.
            (Ord. 154-08. Passed 7-14-08.)