(a) Inspections are required for the following:
(1) Footer: after forms and stakes are in; before concrete is placed.
(2) Foundation: after plaster, waterproofing, tile and gravel; before backfilling.
(3) Framing: after plumbing, wiring, heating, rough chimney and fireplaces are completed; before framing is covered.
(4) Rough insulation inspection: after all wall cavities and similar spaces required to be insulated are ready, and before they are concealed.
(5) Basement floor: before concrete is poured.
(6) Final: after all mechanicals are installed and approved, before occupancy.
(b) In the event the Chief Building Official finds the work is not in accordance with the Building Code at the time of any of the abovementioned inspections, thus requiring additional inspections, the fee for each additional inspection shall be thirty-five dollars ($35.00) payable in advance at the time when the inspection is requested.
(c) Written notice shall be given the office of the Chief Building Official for the above inspections. The Inspector shall make the above inspections, and failure to do so within forty-eight hours shall deem the inspection waived. Failure of the owner or contractor to request inspection shall be deemed a misdemeanor.
(Ord. 66-03. Passed 5-12-03.)