1099.06   PROJECT IMPLEMENTATION AND REIMBURSEMENT.
   (a)   Flood mitigation work completed in accordance with an approved application is reimbursable up to 100% of project costs incurred or the funding caps set forth in the Guidelines, whichever is less. Property owners will not receive reimbursement for funds associated with aesthetic improvements or upgrades to the electrical or mechanical systems unless applicable regulatory codes require the upgrades to complete the project.
   (b)   Property owners must start the project within 60-days of receiving approval from the County. Applicants can request an extension to the start date.
   (c)   Projects completion dates will be determined by the provided project schedule as required by the Guidelines. Applicants must ensure the project is complete by the agreed upon time after which if the project is not complete, funding authorization shall lapse.
   (d)   At the completion of the project, the applicant must provide documentation that they have obtained all required permits and approvals and provide itemized receipts showing payments made for eligible project work.
(Ord. 22-20. Passed 12-14-22.)