SEC. 91.8308. PERMIT FEES.
   (Amended by Ord. No. 171,175, Eff. 7/25/96.)
 
91.8308.1. (Amended by Ord. No. 185,587, Eff. 7/16/18.) Before any application for a Relocation Permit is accepted, a fee shall be paid by the applicant of the cost to the City for the investigation of the condition of the building to be moved and the inspection of the proposed new location. The amount of the fee shall be as shown in LAMC Table 83-A for each main building or for the first accessory building where no main building is to be relocated.
 
   Where an accessory building, in addition to a main building or the first accessory building where no main building is to be moved, is to be relocated from the same location to the same site at the new location, an application fee of $80.00 shall be paid for each such accessory building.
 
91.8308.2.  (Amended by Ord. No. 181,758, Eff. 8/8/11.) In the case of a building located outside the City limits of the City of Los Angeles, an additional fee of $525.00 shall be paid for each application. In addition to the fee, a mileage charge of 65 cents per mile (1609 m) shall be paid for any inspection which is made 10 miles (16090 m) or more beyond City limits. Mileage shall be measured in a straight line from the point 10 miles (16090 m) beyond the City limits which is nearest to the location of the building to be inspected, to the location of the building, and return to said point of departure.
 
91.8308.3. (Amended by Ord. No. 185,587, Eff. 7/16/18.) The application fees required by LAMC Subsections 91.8308.1 and 91.8308.2 shall be in addition to the regular building permit fee required by LAMC Subsection 91.107.2.
 
91.8308.4. (Amended by Ord. No. 185,587, Eff. 7/16/18.) Should a Relocation Permit be denied by the Department solely because the proposed relocation site is not approved, the applicant may, with the consent of the Department, file within six months of the date of the original application an amended application for approval of a new proposed site. An additional fee of $300.00 for each such amended application will be charged. If a Relocation Permit is not obtained within six months after the original application fee is paid, a new application shall be filed and a new application fee paid before the Relocation Permit is issued.
 
91.8308.5. (Amended by Ord. No. 185,587, Eff. 7/16/18.) The provisions of this section shall not apply to the relocation of temporary buildings or structures to be used by a governmental agency for a governmental purpose.